# Electrical
|
||||
|
||||
## Info
|
||||
|
||||
### Lighting Control
|
||||
|
||||
By PDI convention, [[lighting-controls]] are generally "Electrical", not "Lighting".
|
||||
|
||||
## Sequence
|
||||
|
||||
### 1. Preparation
|
||||
|
||||
[[pre-takeoff-research#Wiring Device Selection]]
|
||||
|
||||
1. Read about the project specifications and construction type
|
||||
2. Locate Equipment Schedules
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff all equipment that is not #12
|
||||
2. Go by Drawing in chronological order
|
||||
3. Takeoff Enlarged Drawings
|
||||
4. Do final checklist in electrical takeoff notes
|
||||
|
||||
> [!tip]
|
||||
> It is sometimes easier to rebuild a designation than to modify it.
|
||||
> For designations with existing takeoffs, Right-Click > `Empty Designation`.
|
||||
> The build process can then be completed anew.
|
||||
|
||||
#### Receptacles
|
||||
|
||||
#### Floor Boxes
|
||||
|
||||
##### Poke-Thru's
|
||||
|
||||
#### Mechanical Connections
|
||||
|
||||
`COMMON ASSEMBLIES`/`MECHANICAL CONNECTIONS ...`/
|
||||
|
||||
##### Roof Mounted Equipment
|
||||
|
||||
Unit condensing units
|
||||
|
||||
Put homeruns on the `Area` of the dwelling unit.
|
||||
Put connections on the `Area` of the CU.
|
||||
|
||||
.../`CONDENSOR HOME RUNS`
|
||||
|
||||
.../`CU CONDENSER SLEEVE W/ FLEX - NO HMRN WIRE`
|
||||
|
||||
`NO SLEEVE`:
|
||||
Routed through a "doghouse"
|
||||
(a large weatherproof opening)
|
||||
with several other feeds.
|
||||
Used where drilling openings for individual sleeves
|
||||
would be impractical.
|
||||
|
||||
`PVC SLEEVE`, `EMT SLEEVE`:
|
||||
Routed up through the roof,
|
||||
(optionally through a disconnect)
|
||||
with flex to the equipment.
|
||||
|
||||
Equipment Racks: Max 20 disconnects per rack
|
||||
|
||||
`DISTRIBUTIION`/`TRAPEZE RACK SUPPORT ...`/`...`
|
||||
|
||||
##### Trash Chute
|
||||
|
||||
**Horizontal:**
|
||||
* Check if shown on power drawings as mech connection
|
||||
* If not, use 100ft length
|
||||
|
||||
**Vertical (Riser):**
|
||||
* Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
|
||||
* Uncheck Link 'Enable Livecount'
|
||||
* Takeoff in Typical
|
||||
* Length = average floor to floor height
|
||||
|
||||
#### Homeruns
|
||||
|
||||
##### Lighting
|
||||
|
||||
Takeoff homeruns in Building breakdowns,
|
||||
even serving Amenity spaces.
|
||||
|
||||
> [!info] Breakdowns
|
||||
> * `Area` = "... Building"
|
||||
> * `System` = "Building - BOH ..."
|
||||
|
||||
### 3. Review
|
||||
|
||||
1. Count Car chargers and location
|
||||
Reference in New Issue