vault backup: 2025-10-23 10:52:59
This commit is contained in:
@@ -0,0 +1,134 @@
|
||||
---
|
||||
id: feeders
|
||||
aliases: []
|
||||
tags:
|
||||
- destiny/permanent
|
||||
- status/draft
|
||||
- occupational/systems/feeders
|
||||
- type/guide
|
||||
title: Feeders
|
||||
---
|
||||
# Feeders
|
||||
|
||||
## Info
|
||||
|
||||
### Routing and Structural Considerations
|
||||
|
||||
#### Shear Walls
|
||||
|
||||
Shear walls, like those around stairwells and elevator shafts,
|
||||
may be routed through with special permission.
|
||||
|
||||
#### Post-Tensioned Slabs
|
||||
|
||||
> [!example]
|
||||
> STRUCTURAL SLAB IS AN 8-INCH THICK
|
||||
> UNBONDED POST-TENSIONED TWO-WAY SLAB UNLESS NOTED OTHERWISE.
|
||||
|
||||
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
||||
> No affect on takeoff. Routing in slab still possible.
|
||||
|
||||
> [!cite] Joel Jansen 2025-08-21, in reference to Belle Meade Plaza (pp.)
|
||||
> PT slabs do have some affect on takeoff.
|
||||
> 3in conduit can not be run in an 11in PT slab.
|
||||
|
||||
#### Pan Deck Slabs
|
||||
|
||||
> [!example]
|
||||
> STRUCTURAL SLAB IS 3 1/2 INCHES OF NORMALWEIGHT CONCRETE
|
||||
> ON 3-INCH COMPOSITE STEEL DECK UNLESS NOTED OTHERWISE.
|
||||
|
||||
> [!cite] Joel Jansen 2025-08-15, in reference to Belle Meade Plaza (pp.)
|
||||
> Do not route in slab.
|
||||
|
||||
#### Fire Rated Feeders
|
||||
|
||||
PDI estimating practice is to run all "emergency" feeds
|
||||
(life-safety or just standby)
|
||||
in a 2-hour rated assembly.
|
||||
This usually requires no change to takeoff for high-rises
|
||||
since electrical riser rooms are themselves fire-rated.
|
||||
|
||||
* RHW-2 insulated conductors in conduit -- "Lifeline Cable"
|
||||
* 2-hour rated metal clad cable -- "Vitalink"
|
||||
|
||||
### Formatting
|
||||
|
||||
All feeder takeoff descriptions should be prefixed with `<parent> TO <child>`
|
||||
|
||||
> [!cite] Joel Jansen, in reference to Omni Hotels Raleigh (pp.)
|
||||
> It is acceptable to use typicals for identical feeders
|
||||
> (i.e. meter centers fed from bus plugs)
|
||||
> so long as the typical is in the Feeders `Area`.
|
||||
|
||||
## Sequence
|
||||
|
||||
### 1. Preparation
|
||||
|
||||
Read about the project specifications and construction type:
|
||||
* Deck thickness
|
||||
* Wiring methods
|
||||
* Conductor material
|
||||
* Wire terminations (set-screw acceptable or compression required?)
|
||||
|
||||
Locate:
|
||||
* Riser Diagram
|
||||
* Feeder Schedule (if present)
|
||||
* Main Electrical rooms and panel locations
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
Run parallel to building lines
|
||||
and route through corridors where possible.
|
||||
|
||||
> [!important]
|
||||
> All takeoffs in Systems with names including "site"
|
||||
> should be in "Site" Area, Phase, and Bid Item breakdowns.
|
||||
|
||||
For adjacent panels, use a minimum 10ft length.
|
||||
|
||||
#### Adders
|
||||
|
||||
Use the difference in elevation between equipment
|
||||
or 10ft, whichever is greater.
|
||||
|
||||
Add an additional 5ft (total 15ft) for site runs
|
||||
(primaries, secondaries, etc.).
|
||||
|
||||
#### Primaries
|
||||
|
||||
Usually only empty conduit if included.
|
||||
|
||||
#### Secondaries
|
||||
|
||||
##### Wiring on Vault Racks
|
||||
|
||||
Where secondary conductors run on racks in utility vaults
|
||||
manually set the length of conduit,
|
||||
measure the wire length,
|
||||
add 20ft in addition to previously mentioned adders.
|
||||
|
||||
#### Feeders
|
||||
|
||||
`Area` = "01 - Feeders/Risers Building"
|
||||
for all feeders, no matter the location.
|
||||
|
||||
#### Bus Duct
|
||||
|
||||
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`BUS DUCT`
|
||||
|
||||
#### Conductor Support
|
||||
|
||||
![[nfpa-70_300_general-requirements#300.19 Supporting Conductors in Vertical Raceways.]]
|
||||
|
||||
`ITEM DATABASE`/`CONDUIT & FITTINGS`/`CABLE SUPPORT / WEDGES`/`... COMPLETE FITTING`/...
|
||||
|
||||
#### Grounding
|
||||
|
||||
See [[grounding]].
|
||||
|
||||
#### Sleeving
|
||||
|
||||
See [[sleeving]].
|
||||
|
||||
### 3. Review
|
||||
Reference in New Issue
Block a user