@@ -71,7 +71,7 @@ Manage Styles > Import from template :LiDownload: > "ConEst"
### Setup Breakdowns ### Setup Breakdowns
Replace the `Area`s with those created in [[pdi-conest-project-setup#Setup WBS]] Replace the `Area`s with those created in [[conest-project-setup#Setup WBS]]
> [!important] > [!important]
> Do not copy Systems from WBS Accubid Setup. > Do not copy Systems from WBS Accubid Setup.
+2 -2
View File
@@ -5,12 +5,12 @@ tags:
- occupational - occupational
- type/media - type/media
- exclude-from-word-count - exclude-from-word-count
up: "[[pdi-pre-takeoff-confirmation]]" up: "[[conest-pre-takeoff-confirmation]]"
--- ---
# ConEst Pre-Takeoff Email Template # ConEst Pre-Takeoff Email Template
%% %%
Email template for use in [[pdi-pre-takeoff-confirmation]]. Email template for use in [[conest-pre-takeoff-confirmation]].
This template effectively replicates the official template This template effectively replicates the official template
originally written in Microsoft Word. originally written in Microsoft Word.
+2 -2
View File
@@ -16,9 +16,9 @@ aliases:
## Prerequisites ## Prerequisites
1. [[pdi-conest-project-setup|Project setup]] 1. [[conest-project-setup|Project setup]]
2. [[pre-takeoff-research|Pre-takeoff research]] 2. [[pre-takeoff-research|Pre-takeoff research]]
3. [[pdi-pre-takeoff-confirmation|Pre-takeoff confirmation]] 3. [[conest-pre-takeoff-confirmation|Pre-takeoff confirmation]]
4. [[conest-unit-matrix|Create unit matrix]] 4. [[conest-unit-matrix|Create unit matrix]]
5. [[conest-wbs-setup|WBS setup]] 5. [[conest-wbs-setup|WBS setup]]
6. [[conest-accubid-setup|Accubid setup]] 6. [[conest-accubid-setup|Accubid setup]]
+1 -1
View File
@@ -46,7 +46,7 @@ to which Josh agreed.
2021 IECC applies. 2021 IECC applies.
Josh wants [[pdi-pre-takeoff-confirmation]] Josh wants [[conest-pre-takeoff-confirmation]]
to ask if lighting control is "as shown" or "to code", to ask if lighting control is "as shown" or "to code",
I objected that "to code" as interpreted by Bid I objected that "to code" as interpreted by Bid
is not necessarily _to code_ in truth. is not necessarily _to code_ in truth.
+1 -1
View File
@@ -23,7 +23,7 @@ estimator and senior tasks.
#### 1. Pre-Takeoff Email #### 1. Pre-Takeoff Email
[[conest-pre-takeoff-email-template]] used correctly: [[conest-pre-takeoff-email-template]] used correctly:
[[pdi-pre-takeoff-confirmation]] executed correctly. [[conest-pre-takeoff-confirmation]] executed correctly.
#### 2. Accubid Extension Pricing #### 2. Accubid Extension Pricing
+1 -1
View File
@@ -14,7 +14,7 @@ daily: "[[2026-03-25]]"
Meeting lead by [[josh-ford]] Meeting lead by [[josh-ford]]
regarding [[conest-pre-takeoff-email-template#Tasks/Quotes Needed for WBS]] regarding [[conest-pre-takeoff-email-template#Tasks/Quotes Needed for WBS]]
for [[pdi-pre-takeoff-confirmation]]: for [[conest-pre-takeoff-confirmation]]:
Intent is to reduce WBS turnaround, Intent is to reduce WBS turnaround,
reduce time spent sitting on WBS's completed reduce time spent sitting on WBS's completed
+2 -2
View File
@@ -10,7 +10,7 @@ daily: "[[2026-05-14]]"
## 303 Mariposa Residence Pre-takeoff Confirmation Email Review ## 303 Mariposa Residence Pre-takeoff Confirmation Email Review
Consultation with [[josh-ford|Josh]] Consultation with [[josh-ford|Josh]]
regarding [[pdi-pre-takeoff-confirmation]] regarding [[conest-pre-takeoff-confirmation]]
for [[303-mariposa-residence]]. for [[303-mariposa-residence]].
The project being a single family home, The project being a single family home,
@@ -68,6 +68,6 @@ Add new line:
#### Other #### Other
Josh noted that [[conest#ConEst Senior Estimator|seniors]] Josh noted that [[conest#ConEst Senior Estimator|seniors]]
appreciate the new [[pdi-pre-takeoff-confirmation]] process appreciate the new [[conest-pre-takeoff-confirmation]] process
because they feel more familiar with the job because they feel more familiar with the job
when in [[conest-senior-review]]. when in [[conest-senior-review]].
+1 -1
View File
@@ -8,7 +8,7 @@ daily: "[[2026-05-15]]"
Follow-up to [[2026-05-14_15-31-50]]: Follow-up to [[2026-05-14_15-31-50]]:
At 09:32 [[joshua-komis]] responded At 09:32 [[joshua-komis]] responded
to our [[pdi-pre-takeoff-confirmation]] for [[303-mariposa-residence]] to our [[conest-pre-takeoff-confirmation]] for [[303-mariposa-residence]]
and, in contradiction to our conversation yesterday, and, in contradiction to our conversation yesterday,
confirmed we are to utilize metal boxes in our takeoff. confirmed we are to utilize metal boxes in our takeoff.
There was no mention of the change in direction. There was no mention of the change in direction.
+1 -1
View File
@@ -22,7 +22,7 @@ aliases:
> including [[wiring-method-selection]] and [[wiring-device-research]], > including [[wiring-method-selection]] and [[wiring-device-research]],
> before beginning takeoff. > before beginning takeoff.
1. [[pdi-conest-project-setup#Create Unit Matrix|Create Unit Matrix]] 1. [[conest-project-setup#Create Unit Matrix|Create Unit Matrix]]
2. [[conest-accubid-setup#Create Unit Typicals|Create Unit Typicals]] 2. [[conest-accubid-setup#Create Unit Typicals|Create Unit Typicals]]
## Takeoff ## Takeoff