id: 2026-05-22T11:57:18-0400
|
||||
title: 2026-05-22 11:57:18
|
||||
tags: []
|
||||
daily: "[[2026-05-22]]"
|
||||
---
|
||||
# 2026-05-22 11:57:18
|
||||
|
||||
## ConEst's Purpose Considering its Accuracy
|
||||
|
||||
I removed [[2026-05-21_16-18-20]]'s plot
|
||||
because I screwed up the error calculation.
|
||||
After more rigorous investigation
|
||||
and more recent project data
|
||||
(the same new bids are based on)
|
||||
I'm happier with this one.
|
||||
|
||||
![[pdi-estimating-error-kde.png]]
|
||||
|
||||
The plot suggests that [[conest]]'s role
|
||||
is not in decreasing cost [[uncertainty]],
|
||||
because it does not appear to do so more than marginally.
|
||||
|
||||
I'm lead to speculate that our purpose is in determining crew loading,
|
||||
which is cool with me,
|
||||
labor is the more interesting part of [[construction-estimating]],
|
||||
however our methods are not well suited to the purpose.
|
||||
After all, the majority of it is calculated in [[ms-excel]].
|
||||
See [[pdi-labor-plan]].
|
||||
|
||||
> A less cautious man than I might wonder
|
||||
> if the negative bias apparent in Bid and ConEst
|
||||
> is indicative of systematic [[incentives|incentive]] gaming,
|
||||
> since if it we could change nothing of our process
|
||||
> and simply add contingency to address it.
|
||||
|
||||
***
|
||||
|
||||
> Our use of "WBS" is technically inaccurate.
|
||||
> The [[pdi-wbs|PDI "WBS"]] is more accurately called
|
||||
> [[earned-value-management#Schedule|the project schedule]],
|
||||
> which is the document which defines the planned value of each task.
|
||||
> On the other hand, project schedule is a terrible name for a specific document,
|
||||
> so I don't blame us for stealing WBS.
|
||||