## 303 Mariposa Residence Senior Review
|
||||
|
||||
[[conest-senior-review]] for [[303-mariposa-residence]].
|
||||
[[conest-senior-review]] for [[303-mariposa-residence]]
|
||||
lead by [[joel-jansen]] and attended by [[zane-meyers]] and [[jared-defanti]].
|
||||
|
||||
### Selling Price
|
||||
|
||||
[[pdi-bid-estimating|Bid]]'s proposal base bid \$800,000
|
||||
[[pdi-bid-estimating|Bid]]'s proposal base bid was \$800,000,
|
||||
but in response to the [[conest-pre-takeoff-confirmation]]
|
||||
[[joshua-komis]] said to add \$65,000 for secondaries.
|
||||
|
||||
Joel messaged [[joshua-komis|Joshua Komis]] to clarify.
|
||||
We found correspondence
|
||||
that the secondaries were sold as $10,000 for conduit
|
||||
and $65,000 for wire.
|
||||
|
||||
Joel messaged Komis to clarify.
|
||||
He responded to use \$875,000.
|
||||
|
||||
### Site Run Adders
|
||||
|
||||
previous direction to use 15ft adders for site runs
|
||||
It would be easier to assume 10ft for all cases
|
||||
Joel agreed
|
||||
Joel questioned the use of 15ft adders for secondaries.
|
||||
I explained their use was based on prior direction he had given below.
|
||||
|
||||
> [!quote] feeders-takeoff.md
|
||||
> #### Adders
|
||||
>
|
||||
> Use the difference in elevation between equipment
|
||||
> or 10ft, whichever is greater.
|
||||
>
|
||||
> Add an additional 5ft (total 15ft) for site runs
|
||||
> (primaries, secondaries, etc.).
|
||||
|
||||
Joel remembered and started to move on.
|
||||
Jared asked if the extra adder was for vertical distance or routing contingency,
|
||||
Joel responded that it was sort of both.
|
||||
|
||||
I suggested that if it may be necessary to adjust them anyway,
|
||||
and "site runs" often being up to interpretation,
|
||||
it may be preferable to assume 10ft to start for all cases
|
||||
where the start and end are on the same level.
|
||||
That is, remove the conditional 5ft extra adder from the script.
|
||||
Joel agreed.
|
||||
|
||||
Mariposa's site runs didn't need adders at all
|
||||
since we added PVC80 stub-ups.
|
||||
@@ -36,6 +63,8 @@ Solar [[feeders-takeoff]] used copper feeder size
|
||||
based on aluminum size shown in Solar set.
|
||||
No change necessary.
|
||||
|
||||
We should have added the solar one-line to LiveCount.
|
||||
|
||||
### Material Pricing
|
||||
|
||||
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
|
||||
@@ -47,8 +76,8 @@ but taken off as 2 counts each.
|
||||
|
||||
### Telecom
|
||||
|
||||
[[telecom-takeoff]] used Cat5e
|
||||
which we assumed, but did not note visibly.
|
||||
[[telecom-takeoff]] assumed Cat5e
|
||||
but we did not note the assumption visibly.
|
||||
|
||||
### Fire Alarm
|
||||
|
||||
@@ -60,13 +89,18 @@ which we assumed, but did not note visibly.
|
||||
assuming a dozen or so interconnected smokes.
|
||||
|
||||
\$26,XXX was the quote
|
||||
for sprinkler monitoring only
|
||||
for sprinkler monitoring only.
|
||||
"only one assembly"
|
||||
|
||||
### Closeout
|
||||
|
||||
#### Sales Tax
|
||||
#### Final Pricing
|
||||
|
||||
[[pdi-accubid-final-price]] 10.35%
|
||||
[[pdi-accubid-final-price]]
|
||||
|
||||
##### Sales Tax
|
||||
|
||||
10.35%
|
||||
|
||||
#### Equipment
|
||||
|
||||
|
||||