@@ -12,7 +12,7 @@ because its single advantage over reference class forecasting
is in itemized pricing,
but this advantage is nullified
by the known phenomenon that the precise
selection of particular items and their quantities
selection of particular items and their quantities
can not be trusted to be exactly accurate
due to uncertainty of project conditions,
and by the observation that material pricing at the time of bid
@@ -22,7 +22,7 @@ The inevitable retort is
"It's an *est*imate, not an *exact*imate,"
or some other such reductive dismissal.
True enough, this method is _a_ way
of getting close to the true answer of project cost and schedule,
of _getting close_ to the true answer of project cost and schedule,
but it's not an intuitive one.
For an organizational process to be economical