id: 2026-05-28T09:17:29-0400
|
||||
title: 2026-05-28 09:17:29
|
||||
tags: []
|
||||
daily: "[[2026-05-28]]"
|
||||
---
|
||||
# 2026-05-28 09:17:29
|
||||
|
||||
## Mariposa Spa Electrical
|
||||
|
||||
[[303-mariposa-residence]]
|
||||
|
||||
~~E2.01 we have 10 pump connections~~
|
||||
~~roughly near where the spa drawings put the pool equipment room~~
|
||||
~~not shown on mech, plumbing, otherwise~~
|
||||
~~despite Keynote 4 "SEE MECHANICAL WATER PIPING DIAGRAM FOR EXACT LOCATIONS OF PUMPS."~~
|
||||
~~We could assume that these are intended for the pool equipment~~
|
||||
~~and delete the takeoff.~~
|
||||
|
||||
> M3.00, being a diagram, does not show exact locations,
|
||||
> _but does show the pumps being used for domestic water._
|
||||
> (Also the diagram suggests
|
||||
> that the pumps may be spread much far than implied by Electrical,
|
||||
> that our takeoff may be missing a large amount of cable.)
|
||||
> (Also four water heaters are shown
|
||||
> which were not shown on electrical.)
|
||||
|
||||
SP400 shows an electrical panel Keynote 16
|
||||
"NOT SHOWN ON PLANS.
|
||||
PROVIDE DISCONNECTS IF PANEL IS NOT IN EQUIPMENT ROOM.
|
||||
IF ELECTRICAL PANEL IS LOCATED IN EQUIPMENT ROOM,
|
||||
THEN THE PANEL MUST BE NEMA-4X RATED..."
|
||||
No panel schedule is provided.
|
||||
|
||||
SP400 Pool Equipment Room is not shown
|
||||
on the Arch, Elec, Mech, or Plumbing sets.
|
||||
It is not shown enclosed, even on the Spa set.
|
||||
It seems like the Spa set was done last
|
||||
with no coordination with other disciplines.
|
||||
|
||||
With no other information I'd assume PVC, LFMC, and NEMA 4X disconnects to all equipment shown on SP400
|
||||
from the Garage panels.
|
||||
|
||||
Water Feature plans are a similar case.
|
||||
|
||||
> [!quote] [[josh-komis]] 2026-05-28 around 10:30 (pp.)
|
||||
> Assume a single-point connection
|
||||
> to a pool equipment panel.
|
||||
> 100A for the spa.
|
||||
> Scope for equipment downstream of the panel
|
||||
> should be excluded.
|
||||
|
||||
Neither [[jared-defanti]] nor I am satisfied with this answer.
|
||||
This would mean excluding a significant number of connections.
|
||||
|
||||
> [!quote] [[joel-jansen]] 2026-05-28 13:10 (pp.)
|
||||
>
|
||||