# Distributed Antenna Systems (DAS)
|
||||
# Distributed Antenna Systems (DAS) Takeoff
|
||||
|
||||
## Info
|
||||
> [!important]
|
||||
> Complete [[emergency-systems-research]] before beginning takeoff.
|
||||
|
||||
### Emergency Responder Radio Communication Systems (ERRCS)
|
||||
> [!info]
|
||||
> See [[emergency-communications-systems]] for information
|
||||
> about Emergency Responder Radio Communication Systems (ERRCS).
|
||||
|
||||
Relevant Standard: NFPA 1225
|
||||
> [!info] Cellular Systems
|
||||
> Less common than ERRCS are "cellular DAS" systems
|
||||
|
||||
### Cellular Systems
|
||||
## Backbone
|
||||
|
||||
Less common than ERRCS are "cellular DAS" systems
|
||||
|
||||
## Sequence
|
||||
|
||||
### 1. Preparation
|
||||
|
||||
Complete [[fire-alarm-takeoff]] preparation and takeoff.
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
#### FACR to Every Elev. Shaft
|
||||
### FACR to Every Elev. Shaft
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO ELEV PIT = ...`
|
||||
|
||||
Match Fire Alarm takeoff Length and Count
|
||||
|
||||
#### FACR to Every Staircase
|
||||
### FACR to Every Staircase
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO STAIRWELL = ...`
|
||||
|
||||
Match Fire Alarm takeoff Length and Count
|
||||
|
||||
#### Stairwell Riser Every 2 Floors
|
||||
### Stairwell Riser Every 2 Floors
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`STAIRWELL RISER EVERY 2 FLRS = 1 1/2" EMT (20') W/ 16X16X6 BOX`
|
||||
|
||||
Create a Stairwell typical on every other floor
|
||||
|
||||
#### FACR to Electric Room
|
||||
### FACR to Electric Room
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO 2HR-RATED RM = 2" PVC40`
|
||||
|
||||
Match Fire Alarm takeoff Length
|
||||
|
||||
#### Electric Room Riser to Every Floor
|
||||
### Electric Room Riser to Every Floor
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`2HR-RATED RM RISER TO EVERY FLR = 2" EMT (15') W/ 16X16X6 BOX`
|
||||
|
||||
Takeoff in every Electric Room
|
||||
|
||||
#### Top 2H Rated Room To Roof
|
||||
### Top 2H Rated Room To Roof
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`TOP 2HR RATED RM TO ROOF = 2" EMT W/ RMC WEATHERHEAD & IMC STUB`
|
||||
|
||||
Use 15' or Height of ceiling on last building level
|
||||
|
||||
#### Horizontal
|
||||
## Horizontal
|
||||
|
||||
CORRIDORS EMT OH = 1 1/2" EMT W/ 16X16X6 BOX EVERY 80'
|
||||
CA.28.31.23
|
||||
@@ -77,5 +71,3 @@ CA.28.31.21
|
||||
1-1/2 through corridors w/ 16x16x6 J-Box
|
||||
|
||||
Length for every corridor/garage
|
||||
|
||||