# Lightning Protection
|
||||
|
||||
## Info
|
||||
> [!info]
|
||||
> See [[lightning-protection]] for more on lightning protection systems.
|
||||
|
||||
### Early Streamer Emission (ESE)
|
||||
|
||||
## Estimate Scope
|
||||
|
||||
May or may not be included, see proposal on [[bpm|BPM]]
|
||||
> [!important] ConEst Scope
|
||||
> Lightning protection takeoff may or may not be necessary,
|
||||
> see proposal on [[pdi-bpm|BPM]].
|
||||
> Only takeoff if LP is included in the base bid.
|
||||
|
||||
### Subcontractors
|
||||
|
||||
Find lightning protection subcontractor quotes on BPM
|
||||
|
||||
> [!tip]
|
||||
> While you have them open, put the quote costs in Accubid.
|
||||
|
||||
Search the quotes for direction on downlead counts, total length, and conduit size
|
||||
Find lightning protection subcontractor quotes on BPM,
|
||||
search for direction on downlead counts, total length, and conduit size
|
||||
|
||||
> [!example]
|
||||
> Contractor to furnish 1,980' of 1" PVC conduit and pull string
|
||||
|
||||
> [!tip]
|
||||
> While you have the quotes open,
|
||||
> put the costs in the Subcontractors tab in Accubid.
|
||||
|
||||
If no quote is available:
|
||||
|
||||
* **Downlead locations** = building corners + additional locations
|
||||
|
||||