# Low Voltage
|
||||
# Low Voltage Takeoff
|
||||
|
||||
## Info
|
||||
> [!important]
|
||||
> Complete [[pre-takeoff-research]],
|
||||
> including [[low-voltage-raceway-selection]]
|
||||
> before beginning takeoff.
|
||||
|
||||
> [!info]
|
||||
> See [[low-voltage-systems]] for more info.
|
||||
|
||||
## Scope
|
||||
|
||||
* Security/Intrusion Detection
|
||||
* Access Control
|
||||
@@ -21,38 +29,7 @@ title: Low Voltage
|
||||
|
||||
Not to be confused with [[telecom]].
|
||||
|
||||
### Routing
|
||||
|
||||
#### Exposed Ceilings
|
||||
|
||||
EMT to accessible space?
|
||||
PVC to MDF?
|
||||
|
||||
#### Devices
|
||||
|
||||
#### Daisy Chaining
|
||||
|
||||
how many devices (if any)
|
||||
|
||||
## Sequence
|
||||
|
||||
### 1. Preparation
|
||||
|
||||
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
||||
* Cabling
|
||||
* Conduit & Pathways
|
||||
* Sleeving
|
||||
2. In the drawings, locate:
|
||||
* Floor plans where LV scope is shown
|
||||
* LV Details
|
||||
3. Read about the project specifications and construction type
|
||||
4. Fill out OneNote
|
||||
|
||||
### 2. Takeoff
|
||||
## Takeoff
|
||||
|
||||
1. Takeoff devices as shown throughout the building
|
||||
2. Takeoff riser conduit as needed
|
||||
|
||||
### 3. Review
|
||||
|
||||
1. Sleeving for riser
|
||||
|
||||