is subject to some debate.
|
||||
-->
|
||||
|
||||
> [!aside] "Plans & Specs"
|
||||
> The oft repeated "per plans and specs" is a gross oversimplification:
|
||||
> The RFP documents are more likely than not
|
||||
> to have one or more irreconcilable contradictions,
|
||||
> or some instance of [[gold-plating]] too egregious to accept.
|
||||
> When ConEst takes of a project "per plans and specs",
|
||||
> we are taking off _Bid's interpretation_ of the RFP documents,
|
||||
> which they must be able to articulate.
|
||||
|
||||
Seek to use the cheapest method,
|
||||
as determined by Senior Construction Estimator
|
||||
and Database Administrator,
|
||||
@@ -33,6 +42,47 @@ as allowed for the situation.
|
||||
|
||||
* [[wiring-method-selection]]
|
||||
* [[wiring-device-research]]
|
||||
* [[emergency-systems-research]]
|
||||
* [[low-voltage-raceway-selection]]
|
||||
|
||||
## General
|
||||
|
||||
1. Read about the project specifications and construction type
|
||||
2. Locate Equipment Schedules
|
||||
|
||||
Read about the project specifications and construction type:
|
||||
* Deck thickness
|
||||
* Wiring methods
|
||||
* Conductor material
|
||||
* Wire terminations (set-screw acceptable or compression required?)
|
||||
|
||||
Locate:
|
||||
* Riser Diagram
|
||||
* Feeder Schedule (if present)
|
||||
* Main Electrical rooms and panel locations
|
||||
|
||||
1. Locate Unit panels and relevant keynotes
|
||||
* bus amps
|
||||
|
||||
2. Read about the project specifications and construction type
|
||||
* partition framing (wood or metal studs)
|
||||
* stud depth
|
||||
* wiring methods (NM or MC)
|
||||
* wiring device plates (decora or standard)
|
||||
* wiring device specs (are 15A devices allowed or minimum N5-20R)
|
||||
* equipment (20A Kitchen and bath)
|
||||
|
||||
Low Voltage
|
||||
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
||||
* Cabling
|
||||
* Conduit & Pathways
|
||||
* Sleeving
|
||||
2. In the drawings, locate:
|
||||
* Floor plans where LV scope is shown
|
||||
* LV Details
|
||||
3. Read about the project specifications and construction type
|
||||
4. Fill out OneNote
|
||||
|
||||
|
||||
## Voltage Drop
|
||||
|
||||
@@ -58,16 +108,3 @@ Some cases to mention:
|
||||
* Deck thickness (minimum 3x conduit outer diameter)
|
||||
* Renovations (may not be able to run in slab)
|
||||
-->
|
||||
|
||||
|
||||
|
||||
## Emergency Systems
|
||||
|
||||
1. Find Fire Alarm plans (if present)
|
||||
2. Locate the following rooms:
|
||||
* Fire Command Center (FCC)
|
||||
* Generator Room
|
||||
* Fire Pump Room
|
||||
* Elevator Control Rooms
|
||||
* Elevator Shafts
|
||||
* Stairwells
|
||||
|
||||