@@ -26,6 +26,15 @@ Where NEC, IBC, and other applicable codes fall in this hierarchy
is subject to some debate.
-->
> [!aside] "Plans & Specs"
> The oft repeated "per plans and specs" is a gross oversimplification:
> The RFP documents are more likely than not
> to have one or more irreconcilable contradictions,
> or some instance of [[gold-plating]] too egregious to accept.
> When ConEst takes of a project "per plans and specs",
> we are taking off _Bid's interpretation_ of the RFP documents,
> which they must be able to articulate.
Seek to use the cheapest method,
as determined by Senior Construction Estimator
and Database Administrator,
@@ -33,6 +42,47 @@ as allowed for the situation.
* [[wiring-method-selection]]
* [[wiring-device-research]]
* [[emergency-systems-research]]
* [[low-voltage-raceway-selection]]
## General
1. Read about the project specifications and construction type
2. Locate Equipment Schedules
Read about the project specifications and construction type:
* Deck thickness
* Wiring methods
* Conductor material
* Wire terminations (set-screw acceptable or compression required?)
Locate:
* Riser Diagram
* Feeder Schedule (if present)
* Main Electrical rooms and panel locations
1. Locate Unit panels and relevant keynotes
* bus amps
2. Read about the project specifications and construction type
* partition framing (wood or metal studs)
* stud depth
* wiring methods (NM or MC)
* wiring device plates (decora or standard)
* wiring device specs (are 15A devices allowed or minimum N5-20R)
* equipment (20A Kitchen and bath)
Low Voltage
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
* Cabling
* Conduit & Pathways
* Sleeving
2. In the drawings, locate:
* Floor plans where LV scope is shown
* LV Details
3. Read about the project specifications and construction type
4. Fill out OneNote
## Voltage Drop
@@ -58,16 +108,3 @@ Some cases to mention:
* Deck thickness (minimum 3x conduit outer diameter)
* Renovations (may not be able to run in slab)
-->
## Emergency Systems
1. Find Fire Alarm plans (if present)
2. Locate the following rooms:
* Fire Command Center (FCC)
* Generator Room
* Fire Pump Room
* Elevator Control Rooms
* Elevator Shafts
* Stairwells