@@ -0,0 +1,118 @@
---
id: 2026-03-10T13:51:32-04:00
aliases: []
title: 2026-03-10 13:51:32
tags:
- authorship/original
- destiny/permanent
- status/draft
- type/timestamped
dg-publish: true
date-created: 2026-03-10T13:51:32-04:00
daily: "[[2026-03-10]]"
weekly: "[[2026-W11]]"
monthly: "[[2026-03]]"
quarterly: "[[2026-Q1]]"
yearly: "[[2026]]"
---
# 2026-03-10 13:51:32
## Charlotte South End Hotel Spec Interpretation
[[charlotte-south-end-hotel|Charlotte South End Hotel]]
### EMT Fittings
> [!quote] Spec 260510 2.4(E)
> EMT - Electrical metallic tubing, "thin wall" zinc coated steel, enameled interior, ANSI C80.3, UL-797,
> assembled using concrete tight and rain tight gland-ring compression threaded type fittings
> except where alternate type fittings are allowable by the NEC
> and authorities have jusrisdiction \[sic\].
> [!quote] Spec 260510 2.4(N)(2)
> EMT connectors - Provide gland ring compression threaded fittings, except-
> * a. Concrete tight double set screw type connectors
> are acceptable in 2 1/2-inch and larger sizes
> in dry locations only.
> [!quote] Joel Jansen 2026-03-10 (pp.)
> Takeoff as specified
### Liquid-Tight Conduit
> [!quote] Spec 260510 2.4(G)
> Liquid-tight flexible metallic raceway
> shall be similar to standard flexible steel conduit
> except encased in liquid tight neoprene outer jacket.
No definition is provided for a liquid-tight flexible non-metallic raceway
> [!quote] Spec 260510 2.4(G)(7) (text decoration added)
> Provide _liquid-tight flexible conduit_
> for each motor and rotating device for power and control, ~~computer room~~[^1]
> and for other equipment requiring adjustments or removal for service
> in mechanical rooms or where subject to moisture or weather.
> [!quote] Joel Jansen 2026-03-10 (pp.)
>
[^1]: I feel fairly confident this is erroneous.
### Voltage Drop
> [!quote] Spec 260510 2.2(C)(4) (text decoration added)
> Sizing of conductors and conduits
> shall be solely the responsibility of the Contractor
> and shall be based on the NEC, [[nfpa-70_310_conductors_for_general_wiring|Article 310]].
> Ampacity shall be equal to, or greater than, the required load specified.
> ==Voltage drop shall be no greater than that allowed by the NEC.==
> [!quote] Dwg. E00-00 "GENERAL PRICING NOTES" Note 9
> PROVIDE ALLOWANCE TO UPSIZE FEEDERS/BRANCH CIRCUITS
> (OVER 100 FEET FOR 120/208V, OVER 200 FEET FOR 277/480V)
> FOR A MAXIMUM OF 3% VOLTAGE DROP.
### Lighting Control
> [!quote] LD 03-XX Typical Master Switch Callout
> MASTER - TO CONTROL ENTRY AND ROOM ONLY. ELECTRICAL ENGINEER TO SPECIFY ENERGY CODE COMPLIANT “MASTER OFF” FOR THE REQUIRED GUESTROOM LOADS. GMLD RECOMMENDS LUTRONS "CODE-SMART" SYSTEM THAT POWERS THE LIGHTING SHOWN HERE AS WELL AS TAKES INPUT FROM THIRD-PARTYDOOR CONTACTS, THERMOSTATS AND OCCUPANCY SENSORS. THIS SYSTEM MEETS THE ENERGY CODE REQUIREMENT TO TURN OFF LOADS AFTER A SPECIFIC PERIOD OF TIME AND ALSO PREVENTS LOADS FROM TURNING ON OR OFF UNEXPECTEDLY IN THE MIDDLE OF THE NIGHT.
Lighting control quote does not include master switches
> [!quote] PDR Lutron Lighting Control Quote 2025-12-10
> (13) Pre-Assembled Processor Panel,
> (14) Athena Centralized Din Lighting Control Panel,
> (14) DALI ESN Panel,
> (14) QS Sensor Module,
> (4) Touchscreen,
> (112) QS Wired Keypads,
> (2) Partition Sensor,
> (31) Wired Occupancy Sensor,
> (2) 5 Contact Closure Inputs and 5 Relay Outputs
> [!quote] Proposal 2025-12-12, Pricing Summary
> Lighting Controls Lutron (turnkey) $ 850,000
Assuming that this line includes master switches
based on sum of quote and switch allowance
> [!quote] PDR Lutron Lighting Control Quote 2025-12-10, Pricing Summary Turnkey
> Lighting Control: Lutron $ 738,400.00
> [!quote] 2025.12.09 - Charlotte South End Hotel - Bid Sheet v16-4-2, "Add-On Items"
> master switch in guestrooms - TBD | $ 72,023
### EV Chargers
> [!quote] Proposal 2025-12-12, Alternates
> Add: (21) EV-Capable and (3) EV-Installed per Building Connected $ 38,000
Panel LG's schedule (E06-13)
shows (10) 40A/2P circuits
with description "EV CHARGER".
These circuits are not shown on the electrical set,
nor are any chargers besides.
> this is a quote