# Award Analysis
|
||||
|
||||
BPM > Reports > Awards
|
||||
The HUB > HUB Insights > WIGs, KPIs & milestones
|
||||
|
||||
Inception to Date (ITD)
|
||||
|
||||
$$
|
||||
"Overrun $" = "ITD Cost $" - "Baseline Cost $"
|
||||
|
||||
"Overrun %" = "Overrun $" / "Baseline Cost $"
|
||||
|
||||
"Overrun %" = "ITD Cost $" / "Baseline Cost $" - 1
|
||||
$$
|
||||
|
||||
> [!observation]
|
||||
> Curiously, we've decreased expected uncertainty significantly,
|
||||
> but are consistently overbidding by ~13%.
|
||||
|
||||
This observation is likely due to more recent projects still being in their infancy,
|
||||
where costs have not been totally realized.
|
||||