# Estimating Detail
|
||||
|
||||
In [[construction-estimating]], the acceptable level of detail of an estimate is a contentious subject.
|
||||
What's worse, estimators often disagree on what makes an estimate more detailed than another.
|
||||
With our [[risk-oriented-estimating]] approach,
|
||||
detail is essentially the inverse of epistemic [[uncertainty]].
|
||||
|
||||
That said, the correct answer is this.
|
||||
|
||||
> As detailed as possible, given required turnaround and available estimating resources.
|
||||
|
||||
An estimate's detail is irrelevant to its quality.
|
||||
A less detailed estimate is a more [[risk]]y bid,
|
||||
but **it is not the role of the estimator to determine acceptable risk**.
|
||||
|
||||
## Experiment
|
||||
|
||||
Perform a system takeoff (lighting for example) in exacting detail,
|
||||
the maximum amount you would ever consider using,
|
||||
and measure the time required to do so,
|
||||
as well as the cost of the scope.
|
||||
|
||||
Have another estimator takeoff the same scope using the proposed time saving strategy.
|
||||
|
||||
Repeat the test on additional projects.
|
||||
|
||||
Treat the detailed takeoff as the true value
|
||||
and find the error of the time saving strategy.
|
||||
|
||||
$\frac{d\sigma}{dt}$
|
||||
|
||||
### Expectation
|
||||
|
||||
Time-saving strategies will overestimate or underestimate detailed takeoff
|
||||
depending on the assumptions used in their creation.
|
||||