@@ -19,9 +19,11 @@ Follow-up to [[2026-03-19_09-00-43]]
|
||||
> Following up from our meeting yesterday.
|
||||
> Please see attached for the Pre-takeoff template and example.
|
||||
>
|
||||
> * The template is saved here: S:\Estimating\7 ConEst Team\ConEst Process Documents
|
||||
> * The template is saved here:
|
||||
> S:\Estimating\7 ConEst Team\ConEst Process Documents
|
||||
>
|
||||
> * When completed please save in #4. Notes & E-mails within the project folder.
|
||||
> * When completed please save in
|
||||
> #4. Notes & E-mails within the project folder.
|
||||
>
|
||||
> * When distribution to the team,
|
||||
> please send content within the body of the email
|
||||
@@ -30,10 +32,14 @@ Follow-up to [[2026-03-19_09-00-43]]
|
||||
> * Distribution List:
|
||||
>
|
||||
> * To: PCM, Senior Estimator & Estimator
|
||||
> * CC: Senior Construction Estimator, Other ConEst team members on the project, Josh Ford, Corwin Fluit & Jessalyn Williams
|
||||
> * CC: Senior Construction Estimator,
|
||||
> Other ConEst team members on the project,
|
||||
> Josh Ford, Corwin Fluit & Jessalyn Williams
|
||||
>
|
||||
> * We will not use this exact template for Design Builds (remove spec portion of email),
|
||||
> Data Centers, Stadiums or Large commercial projects (We will customize based on SOW)
|
||||
> * We will not use this exact template for Design Builds
|
||||
> (remove spec portion of email),
|
||||
> Data Centers, Stadiums or Large commercial projects
|
||||
> (We will customize based on SOW)
|
||||
>
|
||||
> For the tasks, I will set up a separate meeting to go over that portion,
|
||||
> feel free to leave that portion off the email until after that training.
|
||||
|
||||