@@ -24,7 +24,7 @@ title: Distributed Antenna Systems (DAS) Takeoff
|
||||
|
||||
## Backbone
|
||||
|
||||
### FACR to Every Elev. Shaft
|
||||
### FACR to Every Elevator Shaft
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO ELEV PIT = ...`
|
||||
|
||||
@@ -58,12 +58,14 @@ Takeoff in every Electric Room
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`TOP 2HR RATED RM TO ROOF = ...`
|
||||
|
||||
Use 15' or Height of ceiling on last building level
|
||||
* **Length** = 15ft or height of ceiling on last building level
|
||||
|
||||
## Horizontal
|
||||
|
||||
1-1/2 through corridors w/ 16x16x6 J-Box
|
||||
> [!important]
|
||||
> Usually only for cellular DAS.
|
||||
> Confirm takeoff requirement with [[pdi-estimating#Bid Estimating|Bid]].
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`CORRIDORS ...`
|
||||
|
||||
Length for every corridor/garage
|
||||
* **Length** = Length measured for every corridor/garage
|
||||
|
||||