Direction for [[telecom-takeoff]] and [[low-voltage-takeoff]]
concerning the proper interpretation of "free-air per code"
as used by [[pdi-estimating#Bid Estimating|Bid]] to qualify our scope.
Relevant to [[charlotte-south-end-hotel]].
> [!quote] [[charlotte-south-end-hotel]] Proposal 2025-12-12 Ex. B Notes
> [!quote] Charlotte South End Proposal 2025-12-12 Ex. B Notes
> * All Fire Alarm and Low Voltage cabling
> is to \[be\] installed via free-air
> in all areas excepted \[sic.\] by code
Strictly speaking, requirements for communications wiring
(governed by [[nfpa-70_national-electric-code#^ch8|NEC Chapter 8]])
(governed by [[nfpa-70_national-electric-code#Chapter 8 Communications Systems|NEC Chapter 8]])
are minimal.
> [!quote] [[joel-jansen]] 2026-03-24 (pp.)
> If rough-in for Telecom or a Low Voltage system is included,
> even if qualified as "free-air per code" or similar,
> always provide backboxes and conduit stub-ups for outlets
> in other than units.
> in other than units[^1].
Joel confirmed this direction is not region specific.
[^1]: Where "free-air per code" applies to units,
conduit and backboxes should never be provided for Telecom or LV.
See [[2026-04-01_13-24-18#Unit Telecom/LV Outlets Where "Free-Air Per Code"]]