@@ -43,8 +43,16 @@ Locate:
|
||||
|
||||
#### Primaries
|
||||
|
||||
Empty conduit.
|
||||
|
||||
#### Secondaries
|
||||
|
||||
> [!info] Vaults and Secondary Connections
|
||||
> In utility vaults, secondary conductors sometimes run on racks,
|
||||
> far past their entrance conduits, to their transformers.
|
||||
> It is necessary to add this distance to the wire makeup,
|
||||
> rather than simply measure the conduit assembly to the transformer.
|
||||
|
||||
#### Feeders
|
||||
|
||||
#### Bus Duct
|
||||
@@ -77,43 +85,12 @@ Locate:
|
||||
|
||||
`ITEM DATABASE`/`CONDUIT & FITTINGS`/`CABLE SUPPORT / WEDGES`/`... COMPLETE FITTING`/...
|
||||
|
||||
#### Grounding
|
||||
|
||||
See [[grounding]].
|
||||
|
||||
#### Sleeving
|
||||
|
||||
See [[sleeving]].
|
||||
|
||||
#### Grounding
|
||||
|
||||
This script is intended to cover both electrical and telecom grounding
|
||||
in lieu of detail sufficient for standard takeoff (e.g. a grounding riser).
|
||||
|
||||
`COMMON ASSEMBLIES`/`GROUNDING`
|
||||
|
||||
##### System Grounding
|
||||
|
||||
> Area: "01 - Feeders/Risers Building"
|
||||
|
||||
`COMMON ASSEMBLIES`/`GROUNDING`/`GND = #3/0 & 1" CONDUIT - EMT`
|
||||
|
||||
* Length: Measure around the main electrical rooms to stacked
|
||||
* Count: Total number of electrical rooms
|
||||
|
||||
`COMMON ASSEMBLIES`/`GROUNDING`/`(3) ... x 10' CU CLAD GRD ROD & 4"X12" GND BAR`
|
||||
|
||||
* Count: 1
|
||||
|
||||
##### Riser
|
||||
|
||||
> Area: "Typical - Building All Electrical Riser Rooms"
|
||||
|
||||
`COMMON ASSEMBLIES`/`GROUNDING`/`GND = #3/0 & 1" CONDUIT - EMT`
|
||||
|
||||
* Length: 15
|
||||
* Count: 1
|
||||
|
||||
##### Telecom Ground Bridge
|
||||
|
||||
Use only where shown.
|
||||
|
||||
`COMMON ASSEMBLIES`/`GROUNDING`/`TELE/DATA GND BRIDGE, ..., W/ COVER & (60') #6 THHN GREEN`
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||