vault backup: 2025-08-08 14:29:11

This commit is contained in:
2025-08-08 14:29:11 -04:00
parent baca4a962d
commit c11ae391f5
103 changed files with 32531 additions and 37142 deletions
+12 -35
View File
@@ -43,8 +43,16 @@ Locate:
#### Primaries
Empty conduit.
#### Secondaries
> [!info] Vaults and Secondary Connections
> In utility vaults, secondary conductors sometimes run on racks,
> far past their entrance conduits, to their transformers.
> It is necessary to add this distance to the wire makeup,
> rather than simply measure the conduit assembly to the transformer.
#### Feeders
#### Bus Duct
@@ -77,43 +85,12 @@ Locate:
`ITEM DATABASE`/`CONDUIT & FITTINGS`/`CABLE SUPPORT / WEDGES`/`... COMPLETE FITTING`/...
#### Grounding
See [[grounding]].
#### Sleeving
See [[sleeving]].
#### Grounding
This script is intended to cover both electrical and telecom grounding
in lieu of detail sufficient for standard takeoff (e.g. a grounding riser).
`COMMON ASSEMBLIES`/`GROUNDING`
##### System Grounding
> Area: "01 - Feeders/Risers Building"
`COMMON ASSEMBLIES`/`GROUNDING`/`GND = #3/0 & 1" CONDUIT - EMT`
* Length: Measure around the main electrical rooms to stacked
* Count: Total number of electrical rooms
`COMMON ASSEMBLIES`/`GROUNDING`/`(3) ... x 10' CU CLAD GRD ROD & 4"X12" GND BAR`
* Count: 1
##### Riser
> Area: "Typical - Building All Electrical Riser Rooms"
`COMMON ASSEMBLIES`/`GROUNDING`/`GND = #3/0 & 1" CONDUIT - EMT`
* Length: 15
* Count: 1
##### Telecom Ground Bridge
Use only where shown.
`COMMON ASSEMBLIES`/`GROUNDING`/`TELE/DATA GND BRIDGE, ..., W/ COVER & (60') #6 THHN GREEN`
### 3. Extension (Review and Checking)