@@ -10,7 +10,7 @@ daily: "[[2026-01-12]]"
|
||||
### CH3 Executed Contract Revision WBS
|
||||
|
||||
[[executed-contract-revisions]]
|
||||
for CH3 South Nine and CH3 North Four (fka Crystal House III).
|
||||
for "CH3 South Nine and CH3 North Four (fka Crystal House III)".
|
||||
|
||||
For Executed Contract Revisions, Bid GP% must be maintained.
|
||||
In this case a negative variance was added to the buyout budget
|
||||
|
||||