# 2025-08-15 14:15:41
|
||||
|
||||
Exact date of quote unknown.
|
||||
Assumed date is that of commit 85d30c0,
|
||||
the first commit the quote appeared
|
||||
in its previous location [[feeders-takeoff]],
|
||||
formerly "feeders.md".
|
||||
|
||||
> [!cite] [[joel-jansen]], in reference to Omni Hotels Raleigh (pp.)
|
||||
> [!cite] [[joel-jansen]], in reference to Omni Hotels Raleigh (pp.)[^1]
|
||||
> It is acceptable to use typicals for identical feeders
|
||||
> (i.e. meter centers fed from bus plugs)
|
||||
> so long as the typical is in `Area` = "01 - Feeders/Risers ...".
|
||||
|
||||
[^1]: Exact date of quote unknown.
|
||||
Assumed date is that of commit 85d30c0,
|
||||
the first commit the quote appeared
|
||||
in its previous location [[feeders-takeoff]],
|
||||
formerly "feeders.md".
|
||||
@@ -9,7 +9,7 @@ daily: "[[2026-05-14]]"
|
||||
|
||||
## 303 Mariposa Residence Pre-takeoff Confirmation Email Review
|
||||
|
||||
Consultation with [[josh-ford|Josh]]
|
||||
Consultation with [[josh-ford|Josh Ford]]
|
||||
regarding [[conest-pre-takeoff-confirmation]]
|
||||
for [[303-mariposa-residence]].
|
||||
|
||||
|
||||
@@ -7,6 +7,7 @@ daily: "[[2026-05-20]]"
|
||||
# 2026-05-20 13:10:36
|
||||
|
||||
Direction from [[josh-ford]]
|
||||
relevant to [[electrical-takeoff]]
|
||||
on [[303-mariposa-residence]]
|
||||
with application elsewhere as well.
|
||||
|
||||
|
||||
@@ -0,0 +1,86 @@
|
||||
---
|
||||
id: 2026-06-03T14:05:39-0400
|
||||
title: 2026-06-03 14:05:39
|
||||
tags: []
|
||||
daily: "[[2026-06-03]]"
|
||||
---
|
||||
# 2026-06-03 14:05:39
|
||||
|
||||
## 303 Mariposa Residence Senior Review
|
||||
|
||||
[[conest-senior-review]] for [[303-mariposa-residence]].
|
||||
|
||||
### Selling Price
|
||||
|
||||
[[pdi-bid-estimating|Bid]]'s proposal base bid \$800,000
|
||||
|
||||
Joel messaged [[joshua-komis|Joshua Komis]] to clarify.
|
||||
|
||||
### Site Run Adders
|
||||
|
||||
previous direction to use 15ft adders for site runs
|
||||
It would be easier to assume 10ft for all cases
|
||||
Joel agreed
|
||||
|
||||
Mariposa's site runs didn't need adders at all
|
||||
since we added PVC80 stub-ups.
|
||||
|
||||
### Site Low Voltage Duct Bank
|
||||
|
||||
We assumed 2in conduit,
|
||||
but did not note this visibly.
|
||||
|
||||
### Solar Feeders
|
||||
|
||||
Solar [[feeders-takeoff]] used copper feeder size
|
||||
based on aluminum size shown in Solar set.
|
||||
No change necessary.
|
||||
|
||||
### Material Pricing
|
||||
|
||||
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
|
||||
|
||||
### Mechanical Connections
|
||||
|
||||
B-1, B-2 feeders were parallel runs,
|
||||
but taken off as 2 counts each.
|
||||
|
||||
### Telecom
|
||||
|
||||
[[telecom-takeoff]] used Cat5e
|
||||
which we assumed, but did not note visibly.
|
||||
|
||||
### Fire Alarm
|
||||
|
||||
[[fire-alarm-takeoff]]
|
||||
|
||||
> PCM is supposed to keep Systems from
|
||||
|
||||
\$10,000 was my budget
|
||||
assuming a dozen or so interconnected smokes.
|
||||
|
||||
\$26,XXX was the quote
|
||||
for sprinkler monitoring only
|
||||
|
||||
### Closeout
|
||||
|
||||
#### Sales Tax
|
||||
|
||||
[[pdi-accubid-final-price]] 10.35%
|
||||
|
||||
#### Equipment
|
||||
|
||||
#### General Expenses
|
||||
|
||||
"Just the PM so we only need one trip"
|
||||
|
||||
Got rid of APM, Foreman
|
||||
|
||||
Approved Labor Plan created by Bid,
|
||||
approved by (Efren's title)
|
||||
|
||||
only 3mil or above
|
||||
|
||||
coordination study
|
||||
\$15,000 up to x
|
||||
\$25,000 above x
|
||||