## 303 Mariposa Residence Senior Review
|
||||
|
||||
[[conest-senior-review]] for [[303-mariposa-residence]].
|
||||
|
||||
### Selling Price
|
||||
|
||||
[[pdi-bid-estimating|Bid]]'s proposal base bid \$800,000
|
||||
|
||||
Joel messaged [[joshua-komis|Joshua Komis]] to clarify.
|
||||
|
||||
### Site Run Adders
|
||||
|
||||
previous direction to use 15ft adders for site runs
|
||||
It would be easier to assume 10ft for all cases
|
||||
Joel agreed
|
||||
|
||||
Mariposa's site runs didn't need adders at all
|
||||
since we added PVC80 stub-ups.
|
||||
|
||||
### Site Low Voltage Duct Bank
|
||||
|
||||
We assumed 2in conduit,
|
||||
but did not note this visibly.
|
||||
|
||||
### Solar Feeders
|
||||
|
||||
Solar [[feeders-takeoff]] used copper feeder size
|
||||
based on aluminum size shown in Solar set.
|
||||
No change necessary.
|
||||
|
||||
### Material Pricing
|
||||
|
||||
Joel requested pricing for the dimmable receptacles from [[pdi-procurement]].
|
||||
|
||||
### Mechanical Connections
|
||||
|
||||
B-1, B-2 feeders were parallel runs,
|
||||
but taken off as 2 counts each.
|
||||
|
||||
### Telecom
|
||||
|
||||
[[telecom-takeoff]] used Cat5e
|
||||
which we assumed, but did not note visibly.
|
||||
|
||||
### Fire Alarm
|
||||
|
||||
[[fire-alarm-takeoff]]
|
||||
|
||||
> PCM is supposed to keep Systems from
|
||||
|
||||
\$10,000 was my budget
|
||||
assuming a dozen or so interconnected smokes.
|
||||
|
||||
\$26,XXX was the quote
|
||||
for sprinkler monitoring only
|
||||
|
||||
### Closeout
|
||||
|
||||
#### Sales Tax
|
||||
|
||||
[[pdi-accubid-final-price]] 10.35%
|
||||
|
||||
#### Equipment
|
||||
|
||||
#### General Expenses
|
||||
|
||||
"Just the PM so we only need one trip"
|
||||
|
||||
Got rid of APM, Foreman
|
||||
|
||||
Approved Labor Plan created by Bid,
|
||||
approved by (Efren's title)
|
||||
|
||||
only 3mil or above
|
||||
|
||||
coordination study
|
||||
\$15,000 up to x
|
||||
\$25,000 above x
|
||||