tags:
|
||||
- estimating
|
||||
---
|
||||
# Assemblies
|
||||
|
||||
In [[construction-estimating-software]],
|
||||
assemblies are groups of material items
|
||||
representing a specific scope of work.
|
||||
|
||||
Assemblies reduce the effort required for takeoff
|
||||
by grouping related items,
|
||||
for example 3/4" EMT connectors and couplings
|
||||
in addition to conduit.
|
||||
|
||||
Assemblies allow... (in order of necessity):
|
||||
|
||||
1. complex items (devices, conduit runs, etc.) with known proportions to be counted as one.
|
||||
2. changes to be made to measures and counts without recounting an entire area.
|
||||
3. takeoffs to be skimmed for obvious deficiencies that would otherwise be obscured
|
||||
4. changes to be made to project requirements (specifications) without recounting an entire area.
|
||||
|
||||
If we agree on the definition of `Branch Wiring: 2#12 #12G; 3/4"C, EMT; On Structure`
|
||||
and its contents as ratios of its length,
|
||||
then their quantities can be calculated with only one measurement.
|
||||
|
||||
This is how "estimating software" assembly takeoff works,
|
||||
however its a simple generic process,
|
||||
possible with several tools an estimator should be familiar with:
|
||||
|
||||
* `XLOOKUP()` - Excel
|
||||
* `Table.Join` - MS Power Query
|
||||
* `JOIN` - SQL
|
||||
|
||||
## Abstraction
|
||||
|
||||
An abstraction is a model that intentionally ignores details
|
||||
that are irrelevant to problem it is used to solve
|
||||