first commit
This commit is contained in:
@@ -0,0 +1,85 @@
|
||||
---
|
||||
tags:
|
||||
|
||||
---
|
||||
# Risk
|
||||
|
||||
## In Common Use
|
||||
|
||||
Risk, in common parlance, is the chance that something "bad" will happen.
|
||||
As such, it is generally understood as a binary, win/loss relationship.
|
||||
|
||||
This model of [[discrete-probability]] is ubiquitous of [[project-management-tm|Project Management™]],
|
||||
and is the sort assumed when using [[risk-registers]].
|
||||
|
||||
> This scope of work presents a 1 in 10 chance of significant delay.
|
||||
|
||||
## In Cost Estimation
|
||||
|
||||
The prior model is well suited to project management,
|
||||
which (being reductive) cares about "why"s,
|
||||
where cost estimation only cares about the bottom line.
|
||||
|
||||
It is generally not useful for construction cost estimation.
|
||||
Potential impacts sufficient to warrant documenting
|
||||
should usually just be [[proposals#exclusions|excluded]].
|
||||
|
||||
Cost estimators usually understand risk in terms of [[continuous-probability]].
|
||||
|
||||
The reality of cost estimation is that there are _no_ certain costs.
|
||||
Traditional construction estimates give a false impression of certainty
|
||||
because they operate on and return fixed values.
|
||||
With the most generous interpretation, they can be said to evaluate cost
|
||||
in the most likely case of each axis of uncertainty.
|
||||
|
||||
"Escalation" means projecting recent pricing to a later date of purchase
|
||||
based on anticipated market conditions.
|
||||
|
||||
### The Problem
|
||||
|
||||
An incongruity exists between estimators and management.
|
||||
Estimators know that estimation isn't even close to 100% accurate,
|
||||
however for management to admit this would require them to admit to executives
|
||||
that they allowed the bid despite the potential that it would not return the expected margin.
|
||||
|
||||
This is an obviously immature mindset.
|
||||
More competent organizations would attempt to quantify this potential as risk,
|
||||
however words like "risk" and "assumption" are upsetting to management
|
||||
who would maintain that a "good" estimate has no risk or assumptions,
|
||||
so instead of quantifying risk we use qualitative queries and expressions.
|
||||
The usual call-and-response looks something like this:
|
||||
|
||||
> "Are you confident in this price?"
|
||||
> "Yes, I feel good about it."
|
||||
|
||||
The reality of estimation is that it involves approximations, assumptions, and judgment under uncertainty.
|
||||
Incomplete design information, market volatility, and unforeseen site conditions inherently affect accuracy.
|
||||
|
||||
In contrast, management often expect deterministic results,
|
||||
treating estimates as precise forecasts rather than probabilistic assessments.
|
||||
This expectation can stem from a lack of understanding about the estimation process
|
||||
or a desire to simplify communication with higher-level executives.
|
||||
|
||||
The terms "risk" and "assumption" while common in mature parlance,
|
||||
require acknowledgement of [[uncertainty]], a threatening concept
|
||||
when personal accountability is ignorantly placed above organizational responsibility.
|
||||
|
||||
Assuming a manager was interested in preserving risk analysis details,
|
||||
frameworks for presenting job details usually lack the detail required to do so,
|
||||
and are sometimes even incompatible with the concept of multiple possible prices due to optional scope.
|
||||
|
||||
## ISO 31000
|
||||
|
||||
ISO 31000 defines risk as the "effect of [[uncertainty]] on objectives"
|
||||
therefore referring to positive consequences of uncertainty,
|
||||
as well as negative ones.
|
||||
|
||||
The standard gives a list on how to deal with risk:
|
||||
|
||||
> 1. Avoiding the risk by deciding not to start or continue with the activity that gives rise to the risk
|
||||
> 2. Accepting or increasing the risk in order to pursue an opportunity
|
||||
> 3. Removing the risk source
|
||||
> 4. Changing the likelihood
|
||||
> 5. Changing the consequences
|
||||
> 6. Sharing the risk with another party or parties (including contracts and risk financing)
|
||||
> 7. Retaining the risk by informed decision
|
||||
Reference in New Issue
Block a user