# Estimating Methodologies
|
||||
|
||||
## The 4 Traditional Methodologies
|
||||
|
||||
> [!quote] Defense Acquisition University
|
||||
> There are four principal cost estimating methodologies:
|
||||
> 1. Comparison/analogy,
|
||||
> 2. Parametric,
|
||||
> 3. Detailed engineering/bottom up, and
|
||||
> 4. Extrapolation from actual costs.
|
||||
|
||||
### Comparison / Analogy
|
||||
|
||||
**Pros:**
|
||||
* simple to implement
|
||||
* quick in practice
|
||||
|
||||
**Cons:**
|
||||
* unsatisfying input
|
||||
* unsatisfying output
|
||||
--
|
||||
|
||||
### Parametric
|
||||
|
||||
**Pros:**
|
||||
* quick in practice
|
||||
* nuanced input
|
||||
* accounts for incomplete input
|
||||
* effectively accurate through the entire estimate process
|
||||
* well-suited for automation
|
||||
|
||||
**Cons:**
|
||||
* complex to implement
|
||||
|
||||
### Detailed Engineering / "Bottom-Up"
|
||||
|
||||
**Pros:**
|
||||
* simple to implement
|
||||
* satisfying output
|
||||
|
||||
**Cons:**
|
||||
* slow in practice
|
||||
* unsatisfying input
|
||||
* accuracy and risk depend solely on estimator
|
||||
* output dependent on complete input
|
||||
* ill-suited to automation
|
||||
|
||||
### Extrapolation from Actual Costs
|
||||
|
||||
Depending on the application this is one is either
|
||||
* better described as the previous 3
|
||||
* or not estimating at all.
|
||||
|
||||
## In Other Industries
|
||||
|
||||
There exist articles from software development project management resources
|
||||
stating essentially what I believe to be true,
|
||||
that parametric estimating is _more_ accurate than bottom-up,
|
||||
in contrast to common assumption.
|
||||
|
||||
I suspect that industry tolerance for cost-modeling
|
||||
is related to the cost of estimation.
|
||||
Software is largely impractical to estimate bottom-up,
|
||||
whereas anyone can take off construction scope.
|
||||
|
||||
Alternate theory:
|
||||
tolerance is related to the industry's ability to understand the model.
|
||||
|
||||
Regardless, a continuum emerges:
|
||||
|
||||
```
|
||||
^
|
||||
| Software
|
||||
| Defense
|
||||
| Construction
|
||||
v
|
||||
```
|
||||
|
||||
Industries that would benefit the most from cost-modeling
|
||||
are least likely to consider it a valid method.
|
||||
|
||||
These methods are actually the same, just different levels of abstraction.
|
||||
This can be observed in the _very_ subtle distinction
|
||||
between parametric and analogous estimating,
|
||||
which also exists in my history-oriented/risk-oriented definitions.
|
||||
|
||||
```
|
||||
# of Parameters
|
||||
^
|
||||
| Bottom-Up (100+)
|
||||
| Parametric (10)
|
||||
| Analogous (1)
|
||||
| Extrapolation (0)
|
||||
```
|
||||
|
||||
These different methods are just a response
|
||||
to different levels of requirement specificity.
|
||||
Parametric is obviously more accurate and precise than analogous,
|
||||
however the question not being asked
|
||||
is if there are diminishing returns to estimate specificity.
|
||||
|
||||
Suppose there are, at some point then,
|
||||
there must then be a point at which **risk of human error**
|
||||
outweighs the value of more perfect information.
|
||||