--- id: 2026-04-08T07:42:17-0400 title: 2026-04-08 07:42:17 tags: - status/draft date-created: 2026-04-08T07:42:17-04:00 daily: "[[2026-04-08]]" --- # 2026-04-08 07:42:17 ## _HTMAiPM_ Reference Class Forecasting (RCF) [[hubbard_2025_project-management#Top-down Estimations Reference Class Forecasting]] %% blockquote syntax below is use to indicate paraphrased quotes. standard paragraphs are my extrapolation. %% *** RCF can avoid potentially faulty scaling (square foot area, number of dwelling/sleeping units) *** > If RCF isn't informative (uniqueness bias) > then neither is project manager experience. *** > A **loss exceedance curve** can inform how to price a project under estimate uncertainty. > Contingency can be added to an estimate made with standard methods > sufficient to lower probability of overrun to 5%, for example.