--- id: aliases: [] tags: - authorship/original - destiny/permanent - status/complete - type/minutes title: 2025-11-04 Belle Meade Director Review --- # 2025-11-04 Belle Meade Director Review ## Takeoff Review Reviewed takeoff by system. ### Retail Village Temporary Power Joel changed square foot budgets to temporary pole budgets only due to minimal scope (warm shell). ### Generator Scope Confirmed generator quotes include furnishing docking station. ### Feeder Lengths Confirmed validity of longer feeder lengths: Generator to Tower B ### Grounding Takeoff appears to be missing some or all grounding. To be added if necessary. ### Subfeed Sizing Based on ampacity, subfeeds are oversized. Sizing was per feeder schedule. Takeoff approved unchanged. ### Undercabinet Wiremold Multi-outlet assemblies above unit kitchen countertops were not taken off, nor was branch wiring for the same. Joel to confirm takeoff requirement with bid. ### Amenity Homeruns No homeruns for amenity lighting or electrical were taken off. Joel to add these. > [!info] Circuits per Raceway > Corwin stated that---assuming no overriding specification--- > up to 6 circuits in a raceway are permissible. ### Lighting Control Lighting control takeoff was reviewed, no changes were recommended. > [!info] Lighting Control Pre-Work > Corwin stated that with the imminent changes to lighting control takeoff, > it will be necessary for estimators to more intently consider the design: > noting quantities of lighting zones and controllers, > even where not explicitly shown. ### Telecom Confirmed unit telecom requirements. Backbone was mistakenly taken off in Telecom. ### Retail Fire Alarm Retail village fire alarm devices were taken off free-air, Joel to substitute for EMT. ## Extension Review Reviewed extension quantities and costs. Of particular note were: * conduit * wire * cable * wiring devices ## Labor Plan Review Hours per square foot was lower than expected, this was rationalized as being due to the relatively high portion of garage and shell retail space. %% "Openings per unit" was another metric considered--- higher than expected in this case--- however I didn't catch the significance of this. %%