# Lighting Takeoff ## Fixtures ### Fixture Labor > | Fixture Type | Labor | > | ------------ | -------------- | > | Paddle Fan | 1.5 hrs/ea | > | Pendant | 1-4 hrs/ea[^1] | > | Strip/Cove | 0.083 hrs/ft | > | Site Poles | 1.5 hrs/ea | > | Festoon | 2 hrs/ea | > | All Others | 1 hrs/ea | > > [^1]: Determine exact labor from fixture and size. ### Fixture Branch Length > | Case | Standard Length | > | ------------- | --------------- | > | Site/Courtyard | 50ft[^1] | > | Garage | 50ft | > | BOH | 40ft | > | Corridors | 40ft | > | Interior Amenity | 40ft[^2] | > | Office/Retail | 50ft | > | Exterior Amenity | 50ft | > | Units | 20ft | > > [^1]: Locate the panel and come up with avg. length > > [^2]: See fixture types below for special cases. ### Fixture Branch Wire size > | Case | Wire Size | > | -------------- | --------- | > | Site/Courtyard | #10[^1] | > | Garage | #10 | > | NM Cable | #14[^2] | > | All Others | #12 | > > [^1]: Refer to panel schedules or Site Pole Detail for Site Pole wire size > > [^2]: Kitchen and bathroom fixtures shall be #12 (NOT #14) on wood frame (NM) projects. ### Garage #### Fixtures Use ENT Assembly unless spec requires otherwise. `PVC/ENT ASSEMBLIES`/`GARAGE FIXTURE ENT W/#10 - STEEL OCT RING` `PVC/ENT ASSEMBLIES`/`GARAGE FIXTURE W/T ROD ENT W/#10 - STEEL OCT RING` If PVC, use following assemblies: | Case | Assembly Path | | ------- | -------------------------------------------------------------------------- | | Ceiling | `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` | | Wall | `PVC/ENT ASSEMBLIES`/`... - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP` | #### Homeruns > `System` = "EL - Electrical" Use 1 Homerun for every 3 circuits in Garage Use assembly `Common Assemblies`/`Device Homeruns in Slab/Deck` ### Surface Mount * Wall Mount (Sconce) * Pendant * Linear * Tape * Track | Wiring Method | Assembly Path | | ---------------------------------------------------------------------------- | | NM Cable | `NM ASSEMBLIES`/`RND BOX BAR HNGR...` | | MC Cable | `MC ASSEMBLIES`/`SQ BOX, ROUND P RING & MNTG BRKT...` | | PVC in Ceiling | `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` | | PVC in Wall | `PVC/ENT ASSEMBLIES`/`3/4" PVC W/ 3#12 - STL BOX/TILE RING` | | EMT | `EMT ASSEMBLIES`/`... - SQ BOX & ROUND P RING` | > [!note] > Use lighting control cable assemblies in Amenity areas #### Tape Lighting Also called "cove" or "strip", however those terms are less specific and potentially confusing. Use item `FIXTURE LABOR 1/2HR` and change `Fct 1` to match the calculated labor. > [!note] > Tape lighting length is limited by the "max power length" of the model > (usually measured in millimeters). > Max power length is usually 5000 to 15000 mm (about 16 to 49 ft) > depending on luminous output and voltage. Separate these fixtures by labor, not length ``` A - Tape 0.5hr (1-6ft) - MC #12 40ft A - Tape 1.0hr (7-12ft) - MC #12 40ft A - Tape 1.5hr (13-18ft) - MC #12 40ft A - Tape 2.0hr (19-24ft) - MC #12 40ft A - Tape 2.5hr (25-30ft) - MC #12 40ft A - Tape 3.0hr (31-36ft) - MC #12 40ft A - Tape 3.5hr (37-42ft) - MC #12 40ft A - Tape 4.0hr (43-48ft) - MC #12 40ft A - Tape 4.5hr (49-54ft) - MC #12 40ft A - Tape 5.0hr (55-60ft) - MC #12 40ft A - Tape 5.5hr (61-66ft) - MC #12 40ft A - Tape 6.0hr (67-72ft) - MC #12 40ft A - Tape 6.5hr (73-78ft) - MC #12 40ft A - Tape 7.0hr (79-84ft) - MC #12 40ft A - Tape 7.5hr (85-90ft) - MC #12 40ft A - Tape 8.0hr (91-96ft) - MC #12 40ft A - Tape 8.5hr (97-102ft) - MC #12 40ft A - Tape 9.0hr (103-108ft) - MC #12 40ft A - Tape 9.5hr (109-114ft) - MC #12 40ft A - Tape 10.0hr (115-120ft) - MC #12 40ft ``` ### Recessed * recessed downlight * recessed linear * wall grazer * troffer | Wiring Method | Assembly Path | | ------------- | ------------------------------ | | NM Cable | `NM ASSEMBLIES`/`HI HAT - ...` | | MC Cable | `MC ASSEMBLIES`/`HI HAT - ...` | For crowded puck light areas: measure length between fixtures, round up to the nearest 5ft > [!note] > "HI HAT" refers to a recessed can fixture. ### Undercabinet Fixtures | Wiring Method | Assembly Path | | ------------- | ------------------------------------- | | NM Cable | `NM ASSEMBLIES`/`UNDER CABINET - ...` | | MC Cable | `MC ASSEMBLIES`/`UNDER CABINET - ...` | > [!note] > Takeoff 2 fixtures if jumping over oven Use 10ft #12/2 for MC & NM ### Paddle Fans | Wiring Method | Assembly Path | | ------------- | ----------------------------------------------------- | | NM Cable | `NM ASSEMBLIES`/`RND BOX BAR HNGR...` | | MC Cable | `MC ASSEMBLIES`/`FAN RATED OCT BOX W/ BAR HNGR - ...` | | PVC | `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` | ### Stairwells & Elevators `PVC/ENT ASSEMBLIES`/`... - SLAB BOX / 45 DEG STUBBY` ### Facade > `Phase` = "Facade" Length and Labor will be more than a normal fixture in BOH/Amenity > | Fixture Type | Labor (hrs) | > | ------------ | ----------- | > | Non-Linear | 2 | > | Linear | See above | > 1. `3/4" PVC W/ 3#10 - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP` > * `Length per Unit` = Distance to panel ### Porte Cochere (Drive up Area) Create its own breakout in WBS, and phase in Accubid This is not technically exposed or drop ceiling, but still use PVC ### FAA Lighting > 1. `FIXTURE LABOR`/`FIXTURE LABOR 1HR` > 2. `FESTOON & ROOF ASSEMBLIES`/`Aircraft Warning, 3/4" Conduit GRC/PVC 2#10, 1#10G` ## Site & Courtyard ### Breakdowns > `System` = "FML - Site Fixtures Material & Labor" ### Fixture Assemblies > | Fixture Type | Assembly Path | > | ------------------------------------ | -------------------------------------------------------------------------------- | > | Step Light | `COURTYARDS & LANDSCAPE`/`STEP FIX, 3/4" CONDUIT - PVC40 - ...` | > | Bollard | `COURTYARDS & LANDSCAPE`/`BOLLARD, 3/4" CONDUIT - PVC40 - ...`[^1] | > | Up-light | `COURTYARDS & LANDSCAPE`/`PERMA POST, 3/4" CONDUIT - PVC40 - ...` | > | In-grade up-light | `COURTYARDS & LANDSCAPE`/`3/4" CONDUIT - PVC40, IMC Elbow, ...` | > | Fixtures built into cabanas/pergolas | `COURTYARDS & LANDSCAPE`/`ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...` | > | Handrail light | `COURTYARDS & LANDSCAPE`/`ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...`[^2] | > > [^1]: If we don't own concrete, delete Pre-cast bollard base from assembly > > [^2]: Per Corwin: Hand rail lights should have a rigid 90 stub up and some flex #### Festoon Lighting AKA "string" or "market" lights > 1. `FIXTURE LABOR`/`FIXTURE LABOR 2HR` > 2. `FESTOON & ROOF ASSEMBLIES`/`FESTOON CABLE HANGER & EYE BOLTS - LENGTH` > * `Length per Unit` = Light string length > 3. `COURTYARDS & LANDSCAPE`/`ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...` > * `Length per Unit` = Distance to panel + 15ft