--- id: 2026-03-29T16:01:12-0400 title: 2026-03-29 16:01:12 tags: - status/draft date-created: 2026-03-29T16:01:12-04:00 daily: "[[2026-03-29]]" --- # 2026-03-29 16:01:12 ## AACE Estimate Classification [Association for the Advancement of Cost Engineering (AACE)](https://web.aacei.org/) AACE International Recommended Practice No. 18R-97 | Estimate Class | Expected Accuracy (Low) | Expected Accuracy (High) | | ------------------------------------------ | -----------------------:| ------------------------:| | Class 5: Concept Screening | -20% to -50% | +30% to +100% | | Class 4: Study or Feasibility | -15% to -30% | +20% to +50% | | Class 3: Budget, Authorization, or Control | -10% to -20% | +10% to +30% | | Class 2: Control or Bid/Tender | -5% to -15% | +5% to +20% | | Class 1: Check Estimate or Bid/Tender | -3% to -10% | +3% to +15% | ![](https://library.aacei.org/pgd01/PGD01_Figure1.png)