--- id: aliases: [] tags: - authorship/original - destiny/permanent - occupational/takeoff/electrical - status/draft - type/guide title: Lighting Controls Takeoff --- # Lighting Controls Takeoff > [!info] > See [[lighting-controls]] for more on lighting controls systems. > [!info] "Local Control" as a PDI proposal qualification > The term "local control only" is sometimes used to indicate > no consideration for _any_ lighting control beyond standard devices, > (with `$D`'s being the triac type) > however, this phrasing is ambiguous and non-universal. > Confirm with [[pdi-estimating#Bid Estimating|bid team]] on what must be included. Determine which Systems and Codes are required: * _IBC/IECC 2021 or later:_ all fixtures 0-10V dimmable. ## PDI Lighting Control Configurations > [!important] > This section is currently not practical ### Stand Alone 0-10V dim -- "LV cable" is 2 conductor Takeoff rough-in for switches and occupancy sensors * **Branch Length** = length of room Takeoff the lighting control relay (DLM) Takeoff an additional controller if receptacles are controlled Takeoff homeruns to the DLM (one per controlled circuit) * Note: Not necessarily per room, several rooms may share a lighting circuit. ### Networked "LV Cable" is [[twisted-pair-cable]] #### Room Controllers No room controllers are necessary, lighting zones are switched from a central lighting control panel (LCP) #### Switches and Sensors Takeoff rough-in for switches and occupancy sensors ?? (only if time based; length based on proximity to switch or occupancy sensor) ?? #### Homeruns Takeoff 1 circuit homerun per lighting zone. ### Wattstopper PDI default configuration #### Room Controllers For all rooms with dimmable fixtures and/or automatically controlled receptacles, take off (1) of either or both as appropriate. `SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`DLM LTG RM CONTROLLER - ...` `SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`REC PLUG CONTROLLER - ...` Takeoff normal power to the controlled load * Add LV cable to fixture branch * Use \#12/3 for controlled receptacles Takeoff rough-in for both the occ sensors and the LV switch `SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`... LV SW - WALL ROUGH IN ...` `SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`... SENSOR LOW VOLTAGE - ROUGH IN ...` * Free air if possible * **Length** = length of room Cat cabling from the controllers on is likely provided by systems * Confirm with chief or quote language #### Corridor Occupancy Sensors If occupancy sensors are shown in the corridors: Takeoff homerun back to the electric room Takeoff (1) DLM controller for each electric room `SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`DLM LTG RM CONTROLLER - ...` ?? Run free-air down corridor ?? * **Length** = Length of corridor Takeoff rough-in for each occupancy sensor shown. #### Network Bridge Check systems quote to determine if network bridges are needed. Takeoff (1) back box for every ==group of rooms you want together== ?? If not showing, put one in every room with a controller ?? #### Homeruns Need a HR into the room for the controllers * Can link multiple controllers (aka rooms) together if you have the same circuit * Go back to closest electric room ## Custom Switch Boxes For switch combinations not in `COMMON ASSEMBLIES`, create [[heating-designations]] based on the most similar.