--- id: 2025-11-04T14:52:05-05:00 aliases: [] title: 2025-11-04 14:52:05 tags: - authorship/original - destiny/permanent - occupational/closeout - occupational/takeoff - status/complete - type/minutes dg-publish: true --- # 2025-11-04 14:52:05 ### Belle Meade Director Review [[estimating-director-review]] for [[belle-meade-plaza]] lead by [[corwin-fluit]], attended by [[joel-jansen]] and myself. #### Takeoff Review Reviewed takeoff by system. ##### Retail Village Temporary Power Joel changed square foot budgets to temporary pole budgets only due to minimal scope (warm shell). ##### Generator Scope Confirmed generator quotes include furnishing docking station. ##### Feeder Lengths Confirmed validity of longer feeder lengths: Generator to Tower B ##### Grounding Takeoff appears to be missing some or all grounding. To be added if necessary. ##### Subfeed Sizing Based on ampacity, subfeeds are oversized. Sizing was per feeder schedule. Takeoff approved unchanged. ##### Undercabinet Wiremold Multi-outlet assemblies above unit kitchen countertops were not taken off, nor was branch wiring for the same. Joel to confirm takeoff requirement with bid. ##### Amenity Homeruns No homeruns for amenity lighting or electrical were taken off. Joel to add these. > [!info] Circuits per Raceway > Corwin stated that---assuming no overriding specification--- > up to 6 circuits per raceway are permissible. ##### Lighting Control Lighting control takeoff was reviewed, no changes were recommended. > [!info] Lighting Control Pre-Work > Corwin stated that with the imminent changes to lighting control takeoff, > it will be necessary for estimators to more intently consider the design: > noting quantities of lighting zones and controllers, > even where not explicitly shown. ##### Telecom Confirmed unit telecom requirements. Backbone was mistakenly taken off in Telecom. ##### Retail Fire Alarm Retail village fire alarm devices were taken off free-air, Joel to substitute for EMT. #### Extension Review Reviewed extension quantities and costs. Of particular note were: * conduit * wire * cable * wiring devices #### Labor Plan Review Hours per square foot was lower than expected, this was rationalized as being due to the relatively high portion of garage and shell retail space. %% "Openings per unit" was another metric considered--- higher than expected in this case--- however I didn't catch the significance of this. %%