--- id: electrical aliases: [] tags: [] --- # Final SOE ## 1. Trash Chute Horizontal: * Check if shown on power drawings as mech connection * If not, use 100ft length Vertical (Riser): * Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...` * Uncheck Link 'Enable Livecount' * Takeoff in Typical * Length = average floor to floor height ## 2. CU/IP * Units Condensing Unit * Mechanical Connection ## 3. Slab Deck Create Area Typicals for every Concrete slab floor: * 'All Building' * 1 every level (Not Roof) * HD: 1 Per Section * 'All Garage' * 1 every level * Takeoff: `ITEM DATABASE`/`MISC PDI PRODUCT`/`MISC MATERIAL - SLAB/DECK & FEEDER`/`MISC MATERIAL - SLAB/DECK (NAILS, PAINT, TAPE, ETC = $250)` * 1 Takeoff each Typical, Count = 1 ## 4. Temporary Power & Lighting ### 4.1 Temp Power ``` Area = "2 - Site" Phase = "Temp Power" System = "TPS - Temp Power Service (Site)" BidItem = "1 - Site" ``` Hoxton Hotel (aka Nashville Hotel) * Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - * SERVICE` ### 4.2A Temp Lighting (Building) ``` Area = "01 - Temp Power Distribution Building" Phase = "Temp Power" System = "TPD - Temp Power Distribution (Gag. & Bldg.)" BidItem = "3 - Building" ``` * Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)` * _Count_ = Building Size = Total GSF - Garage GSF Garden Styles: * Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - T POLE (EACH)` * _Count_ = 1 per 150' per building ### 4.2B Temp Lighting (Garage) ``` Area = "01 - Temp Power Distribution Building" Phase = "Temp Power" System = "TPD - Temp Power Distribution (Gag. & Bldg.)" BidItem = "3 - Building" ``` * Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)` * _Count_ = Garage SF ## 5. Irrigation pumps ``` Area = "2 - Site" Phase = "Temp Power" System = `MISC - Site Miscellaneous` BidItem = "1 - Site" ``` * (3) 3Phase 30A 200' Mech. Con. * Append to name: "Irrigation Pump - "