--- id: aliases: [] tags: - systems/switchgear --- # Switchgear ## Sequence ### 1. Estimate preparation 1. Initial the OneNote 2. In the drawings, locate: * Riser Diagrams * House Panels 3. Copy over the Temporary assemblies from "Ben -1" ### 2. Takeoff 1. Build Items in Distribution: * Panelboards * Switchboards * Transfer SWs * Meter centers * Generator 2. Takeoff Common Assemblies: * XFMRs * Disconnect Switches * Bus Duct 3. Takeoff Items in Item Database: * Wireway (Trough/Gutter) 4. Takeoff Temp Assemblies: * CT Cabinet * Meter * Fire Pump * Fire Pump Controller * SPD/TVSS When building panelboards/switchboards, add terminations according to an example from the schedules. **Do not include feeder terminations.** Items to Avoid: * Tap Boxes * Bus Duct * Vault Room * Anything FPL * Grounding * Elevator Room #### Generator ### 3. Extension (Review and Checking) 1. Generator * Ensure takeoff is in the generator Area and System breakdowns * Put location, quantity, and type on OneNote