| id | aliases | title | tags | dg-publish | |||||
|---|---|---|---|---|---|---|---|---|---|
| PDI Accubid Closeout: Quoted Material |
|
true |
PDI Accubid Closeout: Quoted Material
Important
Quoted material costs must be ==pre-tax==.
Fixtures
- Vendor <- "PDR - {Quote Type}" (e.g. "PDR - Spec/Equal", "PDR - VE")
- Quote <- Per PDI Systems proposal
- Notes <- Quote date
Tip
PDR fixture quotes are usually broken out by area type. It is not necessary to preserve these breakdowns in the estimate. Use the sum total cost in a single Quoted Materials line item.
Switchgear
- Vendor <- Per quote (or "PDI BUDGET" if not available)
- Quote <- Per quote (or Bid Sheet Budget if not available)
- Notes <- Quote Date
Generator
- Vendor <- Per quote (or "PDI BUDGET" if not available)
- Quote <- Per quote (or Bid Sheet Budget if not available)
- Notes <- Quantity, Size in kW, Quote Date