PDI Labor Plan
-
Fill out project basics
-
Check that everything is sorted into correct
PhaseandArea(Extension: Phase - Area) -
Move everything in BUILDING FA systems into FA phase
- Create
Phase= "Fire Alarm" - Check
SystemandBid Item - Scroll through each and select all line items
FA - ... - Set
Phase= "Fire Alarm"
- Create
-
Separate all Phases into their proper corresponding
Labor Factor- Scroll through each
Phase - Change breakdown of everything in each phase to the proper
Labor Factor - Do not move Temp Power (budgets) or site
- Scroll through each
-
Use the Accubid Extension tab to fill out the "Unit Lbr Calc" tab in the labor plan
-
Select extension view "Phase, Sort Code"
-
Open
Phase"UNIT RESIDENTIAL" and "Building - Corridors" -
Go into each Sort code to find the count for each unit item
Code Description 200 rough 300 trim 400 rough wire and cable -
Some items will autofill when you fill out the "Accubid Extension Totals" table on the right
- Anything you make adjustments to, highlight red so it can be reviewed
-
Fill out the "Labor for Concrete Slab/Deck Labor" table on the labor sheet calc tab
-
For the floor counts, if there are multiple buildings, add their total level count together
- 2 buildings that each have 10 floors, input 20 for "number of floors - building
-
Add any useful description to the naming
- Can change "Other" to something more prevalent on the project
-
"pour section rate" refers to the size of each slab that will be poured
- sometimes will be shown on the structural plans
-
"Number of days per..." equals "Pour Section Qty" times 4 or 5
-
-
Check that everything is sorted into correct
PhaseandArea(Extension: "Phase - Area")