Pre-Takeoff Research
%% This note should be arranged chronologically: %%
%%
Requirement Sources
- Drawings
- Project Manual (Specifications)
- GC Narrative
- GC verbal direction
- pdi-bid-estimating proposal
- Bid verbal direction
%%
[!important] Requirement Precedence In case of conflict: Requirements of the plans and specs are superseded by the terms of our proposal, which are superseded by specific direction from the bid team.
%% Where NEC, IBC, and other applicable codes fall in this hierarchy is subject to some debate. %%
[!aside] "Plans & Specs" The oft repeated "per plans and specs" is a gross oversimplification: The RFP documents will---more likely than not--- have one or more irreconcilable contradictions, or some instance of gold-plating too egregious to accept. When ConEst takes off a project "per plans and specs", we are taking off Bid's interpretation of the RFP documents, which they must be able to articulate.
%% The limitations of Bid's authority are currently being questioned, %%
Seek to use the cheapest method (as determined by Senior Construction Estimator and Database Administrator), as allowed for the situation.
- wiring-method-selection
- wiring-device-research
- emergency-systems-research
- low-voltage-raceway-selection
General
Read about the project specifications and construction type:
- Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
- Deck thickness
- Wiring methods
- Conductor material
Locate:
- Main Electrical rooms and panel locations
By System
Feeders
Read about the project specifications and construction type:
- Deck thickness
- Wiring methods
- Conductor material
- Wire terminations (mechanical acceptable or compression required?)
Locate:
- Riser Diagram
- Feeder Schedule (if present)
Subfeeds
-
Read about the project specifications and construction type
- Corridor Ceiling type
-
In the drawings, locate:
- Unit Panel Schedules
- bus amps
- Unit Load Calculations
- Subfeed schedule (if present)
- Unit Panel Schedules
Units
- Read about the project specifications and construction type
- partition framing
- stud material (wood or metal)
- stud depth
- wiring methods (NM or MC)
- wiring device plates (decora or standard)
- wiring device specs (are 15A devices allowed or minimum N5-20R)
- equipment (20A Kitchen and bath)
- partition framing
Electrical
- Locate Equipment Schedules
Fixtures
- Read about the project specifications and construction type
- In drawings, locate:
- Fixture Schedule
- Reflected Ceiling Plans
Low Voltage
-
Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
- Cabling
- Conduit & Pathways
- Sleeving
-
In the drawings, locate:
- Floor plans where LV scope is shown
- LV Details
Telecom
- Locate MDF (aka MTR, MPOE) and IDF Rooms
- Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
- Cabling
- Conduit & Pathways
- Sleeving
- Locate which plans the LV is taken off on
- Locate LV Details
- Read about the project specifications and construction type
- Assume 28" MSDE if not specified.
Voltage Drop
Unless explicitly stated in the plans or specs, conductors are to be sized according to the relevant schedule, without respect for voltage-drop.
%% TODO: Create flow chart for wiring methods. Some cases to mention:
- Deck thickness (minimum 3x conduit outer diameter)
- Renovations (can't route in existing slabs) %%