2.1 KiB
id, aliases, title, tags, up
| id | aliases | title | tags | up | ||||
|---|---|---|---|---|---|---|---|---|
| feeders |
|
Feeders Takeoff |
|
takeoff-scripts |
Feeders Takeoff
Important
Complete pre-takeoff-research, including wiring-method-selection, before beginning takeoff.
Execution
- Primaries
- Secondaries
- Feeders
- Grounding
Formatting
All feeder takeoff descriptions should be prefixed with <parent> TO <child>
It is acceptable to use typicals for identical feeders
(i.e. meter centers fed from bus plugs)
so long as the typical is in Area = "01 - Feeders/Risers ...".1
Routing
Run parallel to building lines and route through corridors where possible.
Important
All takeoffs in Systems with names including "site" should be in "Site" Area, Phase, and Bid Item breakdowns.
For adjacent panels, use a minimum 10ft length.
Adders
Use the difference in elevation between equipment or 10ft, whichever is greater.
Add an additional 5ft (total 15ft) for site runs (primaries, secondaries, etc.).
Primaries
Area= "2 - Site"Phase= "Site"System= "PRI - Primaries"
Usually only empty conduit if included.
Secondaries
Area= "2 - Site"Phase= "Site"System= "SEC - Secondaries"
Wiring on Vault Racks
Where secondary conductors run on racks in utility vaults manually set the length of conduit, measure the wire length, add 20ft in addition to previously mentioned adders.
Feeders
Area= "01 - Feeders/Risers Building"Phase= "Feeders"System= "FRR - Feeders and Risers"
[!info] Garage Feeders
Area"01 - Feeders/Risers Garage" is seldom used. It may be appropriate for totally separate parking garage buildings. Seek clarification before using.
Bus Duct
COMMON ASSEMBLIES/DISTRIBUTION/BUS DUCT/...
Conductor Support
!nfpa-70_300_general-requirements#300.19(A) Spacing Intervals --- Maximum.
ITEM DATABASE/CONDUIT & FITTINGS/CABLE SUPPORT / WEDGES/... COMPLETE FITTING/...
Grounding
See grounding-takeoff.
Sleeving
See sleeving-takeoff.