#topic/construction
Dry utilities: utilities other than "wet" utilities (water, sewer, stormwater), namely power, data, and natural gas.
2026-01-12 13:02:??
#occupational
Joel attributes the #GP Variance to
- missed Polaris lugs for feeders for one building,
- insufficient budget for equipment rental, and
- upfront costs already paid (construction is 50% complete).
He also said that operations accused ConEst of providing insufficient length for subfeeds, which he said was true, but not to the extent accused (only ~600ft missed total).
The award WBS shows $32,382 for equipment rental
I'm dubious of all these explanations, but I don't have another one. I can't find the ConEst folder or Accubid file.