Files
zmVault/2026-01-12_13-02-01.md
T

602 B

2026-01-12 13:02:??

#occupational

Joel attributes the #GP Variance to

  1. missed Polaris lugs for feeders for one building,
  2. insufficient budget for equipment rental, and
  3. upfront costs already paid (construction is 50% complete).

He also said that operations accused ConEst of providing insufficient length for subfeeds, which he said was true, but not to the extent accused (only ~600ft missed total).

The award WBS shows $32,382 for equipment rental

I'm dubious of all these explanations, but I don't have another one. I can't find the ConEst folder or Accubid file.