ConEst Pre-Takeoff Email Template
%% Email template for use in pdi-pre-takeoff-confirmation.
This template effectively replicates the official template originally written in Microsoft Word.
It's my belief that this template can not be implemented without significant modifications specific to the intended project. See implementations elsewhere in this notebook for reference. %%
Hello Team,
Below is a comprehensive list of means & methods for {Project Name}. Please confirm you have received this email and respond with any questions or comments.
- Delivery Method: %% Plans & Specs, Design Build, Design Assist, P&S with Approved VE %%
- Document Stage: %% DD, CD, Permit, GMP, Bid, Awarded %%
- Drawings Date: %% Date %%
- Project Manual Date: %% Date %%
- Proposal Date: %% Date %%
- Takeoff Request Stage: %% Stage 1, Full takeoff, etc. %%
Project Specification Callouts
%% Put page of Drawing or PM after answer %%
- Conduit Execution Plans: %% GRC, coupling specs, etc. %%
- Wire: %% Copper or Aluminum, Acceptable Manufacturers %%
- Cable Uses: %% Branch Homeruns %%
- Steel Box Depth: %% 1-1/2", 2-1/8" %%
- Floor Boxes:
- Box Material: %% Box: PVC, Sheet metal, Cast iron %%
- Cover Material: %% Covers: Brass, Aluminum %%
- Wiring Devices:
- Units: %% 15A Decora %%
- BOH/Common Areas: %% 20A Toggle %%
- Switchboards/Panelboards: %% Acceptable Manufacturers, AL or CU Bussing, Breaker Types (Snap-on, bolt on), ACI Ratings %%
- Transformers: %% Windings AL or CU, K-rating %%
- Generator: %% Acceptable manufacturers, Enclosure Specs, Sound Rating, Remote Tank, Tank Size, Load Banks %%
Project Drawing/Detail Callouts
-
Describe conflicts between drawings / proposal: %% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%
-
Cost drivers in details not shown elsewhere on plans:
PDI System Execution Plan
- Primaries: %% Installation only, (9) 6" PVC %%
- Secondaries: %% PVC UG, GRC Stub-ups, AL %%
- Feeders: %% PVC UG, EMT OH, AL over 100A, 2% VD %%
- Unit Subfeeds: %% MC OH AL, VD per Chart on E5.01 %%
- Units: %% 15A Decora, Insinkerators, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
- Telecom: %% 42" MSDE, No Cable Homeruns, (1) 1" Back to IDF, CAT6 with Stub-ups %%
- EV Chargers: %% 42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %%
- Fire Alarm: %% Free-air where allowed by code. EMT Risers. %%
- DAS: %% Conduit only, Per PDI DAS Design %%
- Low Voltage: %% Free-air where allowed by code. Stub-ups to accessible ceilings. %%
Lighting Control
-
Scope: %% Code Minimum per Energy Code Assigned, P&S, PDI Design %%
-
Area: %% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%
- BOH:
- Corridor:
- Amenity:
- Site/Landscape:
- Garage Entry Point
- Office:
Tasks/Quotes Needed for WBS
- Electrical Constructability Review
- Electrical VDC
- Coordination Study %% Design Build: Not needed. %%
- DAS Public Safety Raceway Design
Thank you,