PDI Accubid Closeout: General Expenses
occupational/closeout
type/guide

PDI Accubid Closeout: General Expenses

Clear Markup % for all lines.

Inspection Permit

  • Field <- "Area"
  • Cost/Unit <- per Bid Sheet tab "Add-On Items", line "Permits"

Off-Site Parking

Only if included in proposal.

"OFF-SITE PARKING (per Month + per Car)":

  • Field <- "Duration Months"
  • Quantity <- Number of vehicles (subject to adjustment)

Certified/Minority Business Enterprise (CBE/MBE)

TODO

WBS Contingency

Clear Field for other than the project's pdi-building-types.

High Density

'WBS CONTINGENCY - LABOR "HD"':

  • Field <- "DirLb Total"
  • Cost/Unit <- 8.5
  • Duration <- 0.01

%% Approved by joel-jansen 2026-02-20 %%

Garden Style, High Rise

In 'WBS CONTINGENCY - LABOR "{PDI Building Type}"':

  • Field <- "DirLb Total"