Temporary Power & Lighting Takeoff
occupational/takeoff
status/draft
type/guide
takeoff-scripts

Temporary Power & Lighting Takeoff

Temp Power Service

[!info] Includes

  • Crane power
    • Area = "2 - Site"
    • Phase = "Temp Power"
    • System = "TPS - Temp Power Service (Site)"
    • BidItem = "1 - Site"

    Takeoff: ITEM DATABASE/TEMPORARY POWER/TEMPORARY POWER - ... SERVICE

    • Count = 1

Temp Power & Lighting

    • Area = "01 - Temp Power Distribution Building"
    • Phase = "Temp Power"
    • System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
    • BidItem = "3 - Building"

    ITEM DATABASE/TEMPORARY POWER/...

    Important

    TEMPORARY POWER, not TEMPORARY LIGHT & POWER

    Garden Style:

    • Takeoff: .../TEMPORARY POWER - T POLE (EACH)1
      • Count = 1 per 150ft per building

    All others:

    • Takeoff: .../* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)
      • Count = Building GSF (Total GSF - Garage GSF)
    • Area = "01 - Temp Power Distribution Garage"
    • Phase = "Temp Power"
    • System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
    • BidItem = "2 - Garage"

    Takeoff: .../* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)

    • Count = Garage GSF

Irrigation Pumps

    • Area = "2 - Site"
    • Phase = "Temp Power"
    • System = "MISC - Site Miscellaneous"
    • BidItem = "1 - Site"

    Takeoff: COMMON ASSEMBLIES/MECHANICAL CONNECTIONS (UP TO 100A)/PVC - LT NM FLEX (CARFLEX)/30A 3PH MECH CONN (200') 3/4" PVC 4#10 - CARFLEX

    • Count = 3

    Prepend to name: "Irrigation Pumps - "


  1. Field constructed assembly of receptacles. Sometimes called a "spider box". ↩︎