303 Mariposa Residence
conest-manager-review for 303-mariposa-residence lead by josh-ford as ConEst Manager attended by joel-jansen as ConEst Senior Estimator and jared-defanti and zane-meyers as ConEst Estimators.
Temporary Power
"Do they really need $10,000 for temp power?"
$2,500 and 50hrs
Site Lighting
Pole Bases
"I would leave it if it's for the bollards. It can't be that much."
Site Low Voltage Duct Bank
Josh okayed assumptions for site runs secondaries
Putty Pads
add putty pads equal to device boxes
Feeders
%% is run from inverter to EM diff size from MDP to inverter? %%
Dimmable Receptacles
Lutron Homeworks devices are thicker, need deep boxes.
Lighting/Shade Controls
Trough
COMMON ASSEMBLIES/DISTRIBUTION/LIGHTING CONTROL PANEL INSTALLATION/_ - LIGHTING CONTROL PANEL INSTALLATION & TROUGH - ...
used 4 section changed labor time from 4 to 6 added 500ft #12/2 NM
Telecom
"I'm surprised this isn't a certified system"
Changed assumed Cat5e to Cat6
"I feel like we don't ever install Cat5 anymore"
"A house on the upper range like this isn't going to go with Cat5"
AV Coordination.pdf TV Specs: 3 Cat6
Fire Alarm
Leaving smokes despite direction for budgetary purposes.
Closeout
Labor Plan
"I don't think you can even do a labor plan." "Just leave it all at 100%."
"I use World (Electric) for everything, I don't care where it is."
Subs
Excavation $5,000
Wireways, Troughs: $1,250
General Expenses
Lower Office Supplies to $2,500
Delete Customer Development
Duration
Approved Labor Plan says 16 months
Removed all under "Jobs > $3mil COGs"
Josh said he removed COGs with Aaron's direction on a job sold at $3.8 million.
Equipment
Removed two-way radio
Material Pricing
Josh: "Put $400 for the Quazite."
Joel: "I put $1,200."
Josh: "You put $1,200? Okay put $500."
Conclusion
surprised by high margin, checked bid takeoff found large cost difference in relocation budget