The lighting drawings for 450-460 James Robertson Parkway Phase II (fka James Roberston Pkwy Mixed Use Development) show occupancy sensors serving electrical rooms. I knew this was understood to be prohibited, but could not have provided a code reference.
nfpa-70_110_requirements#110.26(D) Illumination. is the relevant section.
2026-01-22 11:58:??
#occupational
463 Davison Contract Dates
Effective date: 2026-01-21
- Escrow deposit due by 2026-01-26
- Loan application submitted by 2026-01-26
- Inspection period ends 2026-01-28
- Loan approval due by 2026-02-11
- Title commitment due by 2026-02-27
Closing: 2026-03-04
2026-01-22 14:56:??
#topic/estimating
Accurate Budget Vs. Accurate BOM
Quote
[!quote] Joel Jansen 2026-01-15#2026-01-15 13:27 (pp.) I'd rather have an accurate budget than an accurate BOM.
Context
Analysis
It may be counterintuitive to BOM-oriented estimators (typical of those with an electrical background), but deviating from organization standard practice to make an assembly "more accurate" (read: to make the estimate BOM more closely resemble the construction BOM), may make the budget less accurate.
The review and adjustment process is based on standard practice, so deviations may have unpredictable effects.
Our assemblies do not include screws. It would be more accurate to the BOM to add them, but we budget for that cost in the summary, so to do so would be double dipping.
Though not stated as such, we budget for takeoff-to-install deviations the same way.
\
An organization's takeoff database ought to include exactly what is necessary for takeoff at the acceptable level of detail, and nothing else. It ought to be assumed by estimators that the previous is true, and that acceptable takeoff of any scope must be possible with the contents of the database.