T-Shirt Sizing
"T-shirt sizing" or "T-shirt size estimation" is a method of project estimation characterized by the use of T-shirt sizes representing project scale buckets.
[!example] T-Shirt Sizing in Agile --- Project Management Pathways
XS (1-2 days): Simple UI changes or minor bug fixes
Example: "Update button color on checkout page"
S (2-3 days): Feature enhancements with minimal complexity
Example: "Add product sorting by price"
M (5-7 days): Features requiring moderate integration
Example: "Implement basic search filters"
L (8-10 days): Complex features affecting multiple components
Example: "Create shopping cart functionality"
XL (2+ weeks): Major features requiring breaking down
Example: "Implement payment gateway integration"
The buckets chosen should be wide enough that scale can be confidently estimated after minimal investigation.