Project Management™
this-notebook assumes the reader is more familiar with the construction industry than with any of the other disciplines introduced. As such, "project management" usually refers to construction project management, or more generally to a layman understanding of the term: roughly, "the processes necessary to complete a long-term goal".
Where I am referring specifically to the discipline, as documented by the Project Management Institute, I've opted to humorously style the term as Project Management™ for clarity.
The Problem with Project Management™
The term "Project Management" is deliberately vague, in the hope that generalizing the terminology maximizes its applicability across industries.
There are many core Project Management™ ideas that have no parallel in construction, and there are as many or more critical construction project management problems that Project Management™ doctrine has no good solutions for.
I would posit that, despite its cross-discipline language, Project Management™ practice is only universally applicable to software project management.
That's not to say that it should be overlooked in construction applications. There's no better source for solutions to problems that our industries share. Specialized practices like lean-construction are decades behind PMI. However, consulting Project Management™ for relevant insight requires acknowledging its biases.
Key Differences from Construction
Labor Management
Project Management™ assumes workforce deficits are difficult to fill, and that significant changes are sign of process failure.
- Qualified employees are hard to find
- Project onboarding is extensive
- Diminishing returns start early and are severe
In construction projects, labor is highly dynamic. Workforce necessarily varies greatly through the project's lifespan, and labor reallocation is a regular (weekly) task.
- Qualified employees are relatively plentiful, cost is the bottleneck
- Onboarding is practically nonexistent, new employees are productive on their first day
- Diminishing returns start late and are less pronounced
Basis of Progress
If you assume that labor is a strong predictor of cost, and that your audience can convert between them implicitly, then hours convey both schedule and cost by their nature.
Project Management™ is primarily concerned with schedule, because it assumes that labor is a strong predictor of cost.
- Labor is the greatest (if not only) project cost.
- Labor (and therefore cost) is effectively fixed for a given scope.
As such, Project Managers™ may discuss project cost in hours, with no loss of detail.
In construction projects, labor is known to be a weak predictor of cost.
- Labor is almost always a minority of project cost.
- Functionally equal options have a large spread of possible hours-to-complete and total cost values.
As such, construction project managers must discuss project cost directly.
I believe this difference is one purely of language, and doesn't represent a difference in philosophy. However, it does speak to Project Management™'s tendency to overgeneralize.
Material
The use of labor as a measure of cost is not a difference of philosophy itself, however, Project Management™ is only able to get away with conflating labor and cost because it assumes Material cost is negligible, or that it can be allocated as overhead.
What I'm calling Material cost refers to direct costs not associated with labor. These costs vary wildly, even independent of actual installation requirements, due to gold-plating and owner furnished scope.