PDI Labor Plan
-
Fill out project basics
-
Check that everything is sorted into correct Phase and Area (Extension: Phase - Area)
-
Move everything in BUILDING FA systems into FA phase
- Create a Phase named: "Fire Alarm"
- Check system and Bid Item
- Scroll through each and select all line items
FA - ... - Change Breakdown to "Fire Alarm" phase
-
Separate all Phases into their proper corresponding "Labor Factor"
- Check Phase box
- Start scrolling through beginning with N/A
- Change breakdown of everything in each phase to the proper labor factor
- Do not move Temp Power (buckets) or site
-
Use the Accubid Extension tab to fill out the "Unit Lbr Calc" tab in the labor plan
-
Select the "Phase / Sort Code" extension view
-
Open "UNIT RESIDENTIAL" and "Building - Corridors" phases
-
Go into each Sort code to find the count for each unit item
Code Description 200 rough 300 trim 400 rough wire and cable -
Some items will autofill when you fill out the "Accubid Extension Totals" table on the right
- Anything you make adjustments to, highlight red so it can be reviewed
-
Fill out the "Labor for Concrete Slab/Deck Labor" table on the labor sheet calc tab
-
For the floor counts, if there are multiple buildings, add their total level count together
-
2 buildings that each have 10 floors, input 20 for "number of floors - building
-
Add any useful description to the naming
-
Can change "Other" to something more prevalent on the project
-
"pour section rate" refers to the size of each slab that will be poured (sometimes will be shown on the structural plans)
-
"Number of days per…" is found by multiplying "Pour Section Qty" by 4 or 5
-
-
Check that everything is sorted into correct Phase and Area (Extension: Phase - Area)