ECH3 Executed Contract Revision WBS
For Executed Contract Revisions, Bid GP% must be maintained. In this case a negative variance was added to the buyout budget in order to compensate for an increase in permit fee coverage.
2026-01-12 10:42
Woodbrook Executed Contract Revision Takeoff Check
Unit Dishwasher/Disposal
Drawings show 2 separate duplex receptacles for dishwasher and disposal
Takeoff used DW & DISPOSAL DUAL CIR - ...,
which includes only one receptacle.
According to Joel this takeoff is correct for the scenario.