Telecom

[!info] Scope

  • Telephone
  • Data
  • Cable TV

Important

Not to be confused with low-voltage-takeoff.

Note: Empty Conduit

Where COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/... is specified, FEEDER CONDUIT AND WIRE/... is also acceptable.

"Site Low Voltage Duct Bank"

    • Area = "2 - Site"
    • Phase = "Site"
    • System = "LVD - Site Low Voltage Ductbank"
    • Bid Item = "1 - Site"

    COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...

    • Size and quantity per proposal > drawings > assume (4) 4"C
    • Length = Length measured from MDF to 5ft beyond building footprint

Garden Style: Outside of every building

[!important] Long-Radius Elbows Note requirements for long-radius elbows, substitute items as necessary.

Telecom Vaults

"Quazite Box" polymer concrete enclosure

  1. TEMPORARY ITEMS/Quazite Box ...
    • Material Price = 1000.00
    • Labor Hours = 12.00
    • Sort Code ? = 200

Alternative

  1. COMMON ASSEMBLIES/POLES / EXCAVATION / CORING / UG PULL BX/MANHOLES / PULL BOXES / EXCAVATION / CONCRETE/QUAZITE UG PULL BOXES/...

Backbone Riser

  • Phase = "Building - BOH ..."
  • System = "TC - Telecom Backbone"

(2) 4"C or (4) 4"C if not shown

Horizontal Backbone

    • Drawing = Telecom riser diagram
    • Area = Area of riser room

    COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...

    • Length = Length measured from MDF to IDF
      • Input adder length to reach the level of the IDF (Minimum 15ft).

Vertical Backbone

    • Drawing = Telecom riser diagram
    • Area = "Typical - Building All Levels"

    COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...

    • Delete elbows if unnecessary.
    • Length = Height between floors (Minimum 15ft)

Telecom Backboard

As shown on plans, only if not excluded in proposal.

    • Phase = "Building - BOH ..."
    • System = "TC - Telecom Backbone"

    COMMON ASSEMBLIES/MISC ASSEMBLIES/... PLYWOOD BACKBOARD

    • Count = As shown

Corridor Conduit (Unit MSDE to IDF)

One Takeoff per Area per level

  1. COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...
    • Length = Average of subfeed lengths * # of Units
    • Count = # of Units

Inner Duct

For future use (e.g. fiber)

  1. TEMPORARY ITEMS/MaxCell 3" 3 Cell
    • Material Price = 450.00/C
    • Labor Hours = 12.00/C

Alternative:

  1. COMMON ASSEMBLIES/TELECOM SYSTEMS/INNERDUCT/... (GP)

Devices

As shown on plans. Ignore scope shared with electrical-takeoff. (e.g. floor boxes)

  1. COMMON ASSEMBLIES/TELECOM SYSTEMS/...
    • .../BOH / AMENITY ASSEMBLIES
    • .../SCREWLESS DECORA COVERS UNITS / BOH
    • .../ROUGH IN ASSY

If system is included, take off both rough-in and device assemblies in amenity areas.

If rough-in is included, always provide backboxes and conduit stub-ups for outlets in other than units, even if qualified as "free-air per code" or similar.1