1.6 KiB
id, title, tags, daily
| id | title | tags | daily | |
|---|---|---|---|---|
| 2026-05-14T08:19:37-0400 | 2026-05-14 08:19:37 |
|
2026-05-14 |
2026-05-14 08:19:37
303 Mariposa Residence Pre-takeoff Confirmation Email Review
Consultation with josh-ford regarding pdi-pre-takeoff-confirmation for 303-mariposa-residence.
The project being a single family home, primary estimator jared-defanti requested Josh's aid with precise wording and takeoff assumptions.
Questions
[!quote] Proposal 2026-05-06 _Telecom, Data & Cable TV _
49. Back boxes and stub ups "As required"
Josh confirmed we are to exclude backboxes and stub-ups from takeoff.
Other Direction
Metal Boxes
Highlight 12 AWG minimum, metal boxes; add note "please confirm".
PVC Conduit
Confirmed no PVC except secondaries. Secondaries PVC40 with PVC80 elbow and stub-up.
Project Drawing/Detail Callouts
Delete section conest-pre-takeoff-email-template#Project Drawing/Detail Callouts since empty.
Fire Alarm
Use TERMINAL CABINET not HEAD END.
Did not specifically discuss with Josh, but assuming free-air assemblies for devices
Lighting Control
Confirmed 0-10V/Line voltage dimming per schedule.
Use "Low voltage" (rough-in only) assemblies
Note "rough-in only" in email.
Josh pointed out dimming receptacles.
Low Voltage
Add new line: "Shade Control: System is alternate, do we own rough-in?".
Other
Josh noted that conest#ConEst Senior Estimator appreciate the new pdi-pre-takeoff-confirmation process because they feel more familiar with the job when in conest-senior-review.