Direction from joel-jansen on acceptable conest takeoff for emergency-communications-systems received while working on hilltop-gardens.

Two-Way Horizontal

Relevant to two-way-takeoff:

[!quote] Ben O'Brien's OneNote: Takeoff/(FA RISER + 2-WAY)

  • Horizontal:
    • Length:
      • If shown on Plans (FA/Systems/ etc.)
      • based on FCR to Elevator Lobbies & FCR to Stairwells* (Whichever is longer)

[!quote] joel-jansen via Microsoft Teams @ 2026-05-05 12:12 it defaults to elevator lobbies when no dedicated area of refuge is defined. stairwells they are required for buildings 5 floors AND when the inside door of the stair going to the floor locks so then they would be required every 5th floor

from our FA team

DAS Corridor Assemblies

Relevant to distributed-antenna-systems-takeoff:

[!quote] joel-jansen at around 2026-05-05 11:50 (pp.) Corridor assemblies are usually only necessary for cellular DAS, because Life Safety DAS, especially as designed PDI, does not usually require remote antennas.